What happened
At 30 June 2024, Goodman reported that data-centre projects represented 40 per cent of work in progress. Its global power bank was 5.0 gigawatts across 13 major cities. Half was secured and half was in advanced procurement. Those categories do not mean five gigawatts of operating and leased capacity. The route from a prospective connection to billed rent passes through power agreements, planning, construction, commissioning and occupancy.
A conventional warehouse earns rent for accessible covered space. A data centre requires reliable electrical capacity, cooling and redundancy to an agreed standard. A grid connection promised too late for a tenant’s opening date may be worth less than a smaller connection available now. A developer can secure scarce access early but pay carrying costs for years. Comparing sites by land area alone misses this trade-off.
Goodman Group, an Australian property company, develops and manages warehouses and industrial property in many countries. As demand for data centres grew with cloud computing and artificial intelligence, Goodman began repositioning sites where it could secure power.
In its FY2024 results Goodman reported development work in progress of about A$13.0 billion, with data centres making up 40%. Its global power bank had grown to 5.0 gigawatts across 13 major cities, of which 2.5 GW was secured and 2.5 GW in advanced procurement. A year earlier, data centres had been 37% of work in progress and the power bank 4.0 GW. Goodman reported operating profit of more than A$2 billion but a statutory loss due to property revaluations.
By FY2025 data centres made up 57% of work in progress of A$12.9 billion, and the power bank remained 5.0 GW, with 2.7 GW secured. Goodman expected about 0.5 GW of data centre projects to be underway by June 2026.
Power capacity is not the same as leased, operating data centres. The case shows how investors should distinguish secured power, projects under construction and income-producing assets.
Key moments
Goodman advances data-centre strategy
Year-end power bank measured
Secured and procurement-stage capacity disclosed separately
Global power bank of 5.0 GW across 13 cities in FY2024 (2.5 GW secured, 2.5 GW in advanced procurement); work in progress about A$13bn. Sources: Goodman Group; IT Brief.
The trade-offs at the heart of the case
Measure the date as carefully as the megawatt
A binding offer of power in four years may have little value to a tenant whose current facility lease expires next year. Conversely, a flexible tenant can extract a lower rent by helping a developer commit early to grid work. A power inventory becomes more informative when each entry has an energisation window, dependencies, payment milestones and an alternative use for the land. Compute how much interest and holding expense accumulates if one grid milestone slips. The city with the most prospective megawatts may contribute less near-term cash than a smaller market with signed tenants and firm connections. A data-centre developer can sell powered land, build a shell or fund a more complete facility. Each model earns rent or development profit on a different amount of capital and carries different operational obligations. Comparing reported megawatts across developers without identifying that boundary can produce a false ranking. Determine who supplies cooling equipment, who bears connection costs and when the tenant starts paying. A scarce grid connection gives the developer an option, but its exercise price depends on which building it ultimately promises to deliver.
Testing the evidence
One practical field study would follow sites with secured grid connections. A comparison group could be similar sites awaiting binding power arrangements. Measure time to rent-producing commissioned capacity over equivalent windows and show their levels before the decision. Account for local transmission upgrades and tenant demand in designing the comparison. A widening gap after the event is more persuasive when the earlier paths were similar and neither group experienced another major change at the same time. Use connection agreements with enforceable dates and tenant obligations to reconstruct the decision as it looked at the time. Keep subsequent information in a separate column. Hindsight can establish what eventually occurred, but it cannot establish that a manager could have known it with reasonable confidence beforehand.
For your seminar, paper or interview
- Q1
What would you pay today for a megawatt that is likely to arrive two years after an anchor tenant needs it?
- Q2
How would you use similar sites awaiting binding power arrangements to test changes in time to rent-producing commissioned capacity, while allowing for local transmission upgrades and tenant demand?
- Q3
Compare the recommended course with retaining industrial use until a binding grid agreement and tenant commitment coincide. Which commitment would you make first, and what result would cause you to change course?
- Higher and better use
- Power as a scarce input
- Development pipelines
- Capital partnerships
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
Stage spending against documented grid milestones and tenant commitments. Label megawatts consistently across target, contracted, energised and revenue-producing capacity. Preserve alternative industrial uses where feasible. Capital tied to early-stage sites should earn a development return sufficient to compensate for waiting, including a case in which connection dates move beyond customer demand.
Secure power early
Lock in grid connections on owned sites before demand peaks.
Reposition industrial land
Convert well-located warehouse sites to data centres where power is available.
Use partnerships
Fund large data centre projects with capital partners to limit balance-sheet risk.
What this plan gives up
Shifting to data centres offers higher returns from scarce power and land, but projects are larger and more complex, and depend on a small number of large tenants.
The strongest counter-argument
Waiting for a binding tenant before reserving power preserves capital but may leave the developer unable to offer a credible delivery date. Reserving power first creates an option with carrying costs. Where feasible, include the value of continuing industrial use while decisions remain open. This puts a tangible price on how long the developer can afford to wait. Consider the lender’s view of an unenergised site. The land may provide collateral, but specialised works funded before a power connection is certain may have little recovery value for another user. A project can become less flexible with each construction stage even while reported work in progress rises. Separate recoverable land value from the amount already sunk into a particular design. Then compare the next expenditure with the value of waiting for the power and lease milestones that make it financeable. Ask which tenant could use the current design if the anchor tenant walks away. Its answer sets an indicative economic floor under the value of the work already completed.
Metrics to watch
- Secured power
- Data centre pre-commitments
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- Goodman Group · FY2024 annual report and power bank ↗
- Goodman Group · FY2024 results presentation ↗
- Goodman Group: FY2024 results ↗
- Goodman Group: FY2025 results ↗
- IT Brief: Goodman Group FY2023 data centre expansion ↗
- Image: AI-generated editorial illustration for Simplifying Finance. Illustrative scene.
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.