What happened
Following the December 2004 Indian Ocean tsunami, the Rekompak programme provided grants and technical assistance for community-based reconstruction. A World Bank summary reports that around 15,000 families in Aceh and Nias were helped to repair or rebuild homes and that 176 villages received basic infrastructure grants . A later review places the approach within the broader recovery programme . These counts describe the programme’s outputs. They do not imply that every completed house was identical or that the programme accounted for all regional reconstruction.
The World Bank places the community initiative inside a wider recovery plan for Aceh and Nias . An estimate of the benefit of household control must therefore account for shared roads, water and other infrastructure delivered by the wider recovery effort, which also affected whether families could return.
The tsunami of 26 December 2004 devastated Aceh, and an earthquake struck Nias in March 2005. In the village of Lambung in Banda Aceh, 885 of 1,241 inhabitants died. The Multi Donor Fund for Aceh and Nias, with the World Bank as trustee, financed the Community-based Settlement Rehabilitation and Reconstruction Project, better known as Rekompak, which put reconstruction in the hands of communities.
Grants were paid straight into community accounts in instalments, released as construction progressed. Households formed groups, chose designs with facilitators and engineers, bought materials and hired builders. At least 30 percent of project team members had to be women. Inspections later found that not all houses met seismic standards, so a retrofitting programme strengthened the concrete frames of 1,430 houses at their owners’ request.
The model was then scaled up. After the 2006 Yogyakarta earthquake, Rekompak under the Java Reconstruction Fund rebuilt about 300,000 houses in 18 months. The World Bank later published the approach as a guide, and it has informed reconstruction advice elsewhere, including the Philippines after Typhoon Haiyan in 2013.
Community-driven reconstruction has since been used after disasters in Pakistan, Nepal and the Philippines. The common lesson is that cash to households or communities, combined with technical help and staged payments, tends to produce housing that people actually live in, faster than many centrally contracted programmes. For donors, the Aceh experience also showed the value of a pooled trust fund. The Multi Donor Fund let many governments finance one programme with common rules, rather than running dozens of separate projects with different standards and reporting. Its documents and guides remain freely available to planners preparing for future disasters.
Key moments
Indian Ocean tsunami strikes Aceh
Major earthquake hits Nias
Rekompak begins under the Multi Donor Fund for Aceh and Nias
Approach scaled up after the Yogyakarta earthquake
Programme completed
Mixed units. The Yogyakarta figure is about 300,000 houses in 18 months under the Java Reconstruction Fund. Sources: World Bank.
The trade-offs at the heart of the case
Purchase an occupied home
A unit-cost comparison should include the house, site access, shared services, technical oversight and any unpaid work contributed by residents. One model may look cheaper simply because villagers provide transport or labour outside the construction budget. That contribution can also create ownership and adapt the design to local needs. Record the time cost and the resulting benefit separately. Community control can expose an unsuitable plan earlier. It can also disadvantage households less able to attend meetings, obtain documents or manage a contractor. A centrally procured alternative can buy materials at scale and enforce consistent standards but may deliver inappropriate layouts or sites. The choice is about the allocation of decisions and support, not a universal preference for local or central control.
A completed house has to work as a home
Visit a completed dwelling with the household and check access, water and the outstanding payments for labour and materials. A house counted at physical completion may be difficult to occupy if an adjacent drain or road remains unfinished. Conversely a modestly different layout can reflect a household making better use of its grant. Assess construction quality and household control together before interpreting variation in the finished homes as either waste or success.
Speed versus quality
Communities can rebuild fast because they know local needs and can start without a central contractor. But households with little building experience may cut corners, and seismic standards can slip. Rekompak responded with facilitators, engineers and later retrofitting. The cost of that oversight is part of the true cost of a community-built house.
Who decides where to rebuild
Many families wanted to rebuild where they had lived, close to work and family, even if the land was exposed to future tsunamis. Relocation can improve safety but cuts people off from livelihoods. Community control tends to favour rebuilding in place, which strengthens recovery but may leave some risk in place too.
For your seminar, paper or interview
- Q1
How would you value materials and labour supplied by families?
- Q2
Which homes remain unoccupied despite formal completion?
- Q3
Who will maintain shared drainage after recovery funding ends?
- Q4
How would you tell a finished house from a home ready to occupy?
- Q5
Which inspection contract would serve a remote village fairly?
- Community-driven development
- Grant disbursement in tranches
- Quality assurance
- Disaster recovery financing
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
Giving communities control of reconstruction grants, paid in tranches against progress and backed by technical oversight, produced faster and better-accepted housing than contractor-built schemes. The oversight budget is not optional; the retrofitting programme shows the cost of skimping on it.
Pay in tranches
Release funds as construction stages pass inspection.
Fund technical support
Provide engineers and facilitators to each village.
Include shared services
Budget for water, drainage and access with the houses.
What this plan gives up
Community control speeds recovery and builds ownership but needs strong quality checks.
The strongest counter-argument
Contractor-built housing can be more uniform in quality and easier to audit, and community schemes may place a heavy burden on traumatised households.
Metrics to watch
- Share of houses meeting safety standards
- Occupancy rate of completed houses
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- World Bank: community settlement rehabilitation and reconstruction ↗
- World Bank: Building Indonesia’s Resilience to Disaster ↗
- World Bank: Rekompak results ↗
- World Bank: Rekompak — Rebuilding Indonesia’s Communities After Disasters ↗
- World Bank blog: turning to unity ↗
- ADB: housing component in Aceh and Nias ↗
- Image: A US Navy aerial photograph of tsunami damage in Aceh on 6 January 2005, before the reconstruction assessed here. Photograph credit: U.S. Navy photo by Photographer’s Mate Airman Jordon R. Beesley. Original photograph · Public domain. ↗
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.