Case study · United StatesAutomotive2023–February 2025Last reviewed 22 November 2026

Mercedes-Benz case studiesAmericas case studiesAutomotive case studies

Mercedes-Benz

Which charging station should eight rivals build?

Should a shared charging venture build its next station where demand is strongest or where a missing stop costs its owners car sales?

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Automaker investors8
North American ports targeted≥30,000
Sites under contract>100
01 · The situation

What happened

Two prospective electric-car owners may live within easy reach of a home charger and still hesitate over the same holiday trip. A single unreliable stop can make a long route feel unusable. For Mercedes-Benz, fixing the gap could help sell a car even if the charging station itself earned little. The problem was that the improvement would also benefit buyers of competing cars. IONNA, an automaker-backed charging venture in North America, offered a way to share that investment. It immediately raised a second question: which sites would a group of rivals choose to build first?

Seven automakers, including Mercedes-Benz, announced the initiative in July 2023. IONNA began operations after regulatory approval in February 2024. Toyota joined the other seven as an investor in July that year. The venture described an ambition of at least 30,000 charging ports in North America by 2030. A port is one charging position, and multiple ports can occupy one location. An announcement about ports cannot be read as a count of sites. A long-term network target is also distinct from the number of working ports available on any particular day.

Seven carmakers, including Mercedes-Benz, announced the charging initiative in July 2023, and IONNA began operations in 2024. Toyota joined as the eighth investor in July 2024. The venture aims for at least 30,000 high-powered charging ports in North America by 2030.

In February 2025 IONNA marked its move from beta to national release at its site in Apex, North Carolina, reporting more than 4,400 test sessions with over 80 vehicle models and nearly 63,000 kWh delivered, with more than 100 sites under contract.

02 · Timeline

Key moments

  1. Seven automakers announce the network initiative.

  2. IONNA begins operations, and Toyota joins as an investor in July.

  3. National release is marked at the Apex, North Carolina site.

03 · Exhibit
Exhibit 1 · Carmakers investing in IONNA
automaker investors7At announcement (July 2023)8After Toyota joined (July 2024)

Source: Mercedes-Benz Group; Toyota USA, July 2024.

04 · Core tensions

The trade-offs at the heart of the case

The site the operator wants and the site a carmaker wants

A charging operator may prefer a busy shopping location with heavy existing EV traffic, a convenient grid connection and a customer who buys a drink during the stop. A participating carmaker may prefer a site that fills a long gap on a corridor used by households that have yet to buy an EV. The first location can generate revenue immediately. The second may remove an obstacle to car sales while initially attracting relatively few sessions. Both can be worthwhile, but the parties capturing the economic benefit are different. A consortium can resolve some of this problem by pooling the gains that would otherwise spill over to competitors. It still has to agree how to finance coverage where the station cash flow alone is weak. One manufacturer may already have strong demand in the region while another expects to enter several years later. Who votes for a marginal corridor today, who pays during the time customers are scarce and what happens if forecasts change? Counting investors or announcing a national target does little to answer the governance question at an individual site.

What the beta test did and did not establish

In February 2025 IONNA announced a transition from public beta to national release, marked at its Apex, North Carolina site. It reported more than 4,400 test charging sessions involving over 80 distinct vehicle models and nearly 63,000 kWh delivered. The programme provided evidence about interoperability and practical customer experience. It could not by itself establish the steady-state revenue of a nationwide network. Test vehicles, unusual visit patterns and the geography of the early sites can all make beta users different from future paying customers. IONNA also announced that it had contracted over 100 sites. A contract is one stage on the way to a functioning charging bay. A site can still require utility work, permits, equipment installation, commissioning and testing with vehicles before it earns a dollar from a driver. Conversely a functioning location can be fully operational but inaccessible to a driver because of a payment failure or inaccurate status information. The investment committee needs a schedule from signed site through completed paid session. A count of contracts should sit near the start of that schedule, not at the end. Ask the utility which connection date is binding and whether a smaller first phase could open earlier. The fastest route to a functioning corridor might be four reliable bays this winter followed by more capacity later, even if an eight-bay ribbon cutting would photograph better.

A portfolio with two ways to earn its place

Our editorial recommendation would be to divide candidate sites by how they justify investment. Require mature traffic locations to meet an ordinary station return threshold, measured after power, maintenance, site costs and capital. For coverage sites below that threshold, require participating automakers to identify which routes become viable and document the vehicle demand they believe is at stake. Set an explicit limit on how long a site can draw strategic support before the case is reviewed. This preserves the opportunity to build a genuinely valuable network without treating every low-return station as essential infrastructure. The strongest objection is that early traffic is a poor guide to the value of a network still full of gaps. A driver may ignore the first site on a corridor until the third location completes a reliable route. The board can test clusters of complementary sites and measure changes in completed journeys and repeat use after the connection opens. In markets where practical, compare routes with similar vehicle populations and competing chargers. The comparison will remain imperfect, but it is more informative than counting each isolated opening as an independent success. For Mercedes, the long-run test is whether access reduces the objections that cause an otherwise willing customer to choose another powertrain. For IONNA, it is whether enough reliable sessions yield a return after all site and network costs. Agreeing up front how to measure both outcomes gives eight investors a reason to support a site that one might never build alone. It also gives them a fair way to decline a ninth attractive pin on a map when the numbers behind it do not justify the investment.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    How do a charging port and a site differ?

  2. Q2

    Which corridor would a carmaker fund that an operator might reject?

  3. Q3

    At $8 of contribution per session, how many sessions cover the site’s annual fixed costs?

  4. Q4

    What did testing across more than 80 vehicle models establish?

  5. Q5

    How can the partners test whether a missing stop prevents vehicle sales?

Frameworks worth applying
  • Industry consortium
  • Network economics
  • Site selection
  • Shared infrastructure
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

We think a shared network makes sense for its owners because reliable charging helps sell every member’s electric cars. The venture should place stations where demand justifies them, while the owners agree how to fund strategic sites that support car sales but earn less on their own.

  1. Separate two kinds of site

    Distinguish commercial stations from strategic ones.

  2. Fund strategic sites jointly

    Agree how owners share their cost.

  3. Measure reliability

    Publish uptime and session success rates.

What this plan gives up

Pooling investment spreads cost but requires eight carmakers to agree on priorities.

The strongest counter-argument

Some argue charging is best left to specialist operators, with carmakers focusing on vehicles.

Metrics to watch

  • Ports installed against the 30,000 target
  • Session success rate
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.