Who finances the wait for a tax certificate under Obras por Impuestos?

A business can help deliver a public project today and receive an instrument usable against eligible tax obligations later. The time between those events has a price. Peru’s Obras por Impuestos mechanism is a financing case even when the public project itself charges no user fees.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Enabling legislationLaw 29230
MechanismObras por Impuestos
Regional and local certificateCIPRL
01 · The situation

What happened

Under the framework created by Law 29230 in 2008, participating private companies can advance eligible expenditure on prioritised public investments and obtain certificates under the applicable process. Official guidance describes the CIPRL used for regional and local public investment. A company’s expenditure, the value accepted by the public counterparty, the certificate issued and tax offset achieved need not fall in the same reporting period. Each has separate supporting documentation.

Map the procedure in cash terms. A contractor may be paid as work proceeds. An inspection can identify a change that has not been approved. Certification and use against a qualifying tax obligation occur later. The public authority gets an asset or service and faces the fiscal consequences prescribed by the framework. Treating the arrangement as a donation understates its economic cost to the public. Treating a certificate as cash received on expenditure day understates the firm’s financing requirement.

Obras por Impuestos, which means works for taxes, is a mechanism created by Law 29230 in 2008. It allows private companies to finance and carry out public investment projects and recover the cost by reducing their future income tax payments.

Projects must be prioritised by public entities, such as regional governments, municipalities, universities and national ministries. The company finances and builds the project, and the public entity supervises it.

For regional and local projects, the company receives certificates known as CIPRL, which it can use to pay income tax. For national projects, a similar certificate called CIPGN is used.

The mechanism was designed to address a long-standing problem in Peru: many regional and local governments receive mining royalties and other revenue but lack the capacity to plan and execute projects quickly.

Use of the mechanism has grown sharply. According to ProInversión, awards reached about S/4.2 billion in 2024, and El Peruano reported a record S/5.18 billion in 2025 through 501 projects.

From 2009 to the end of 2025, about 1,105 interventions were awarded for a cumulative S/16.97 billion, with the participation of 393 private companies.

Large banks and mining companies are among the main participants. Projects cover education, health, transport, sanitation and public security.

Similar models exist elsewhere: Colombia has a works-for-taxes scheme, and many countries use tax credits to encourage private investment in public goods.

For companies, the mechanism offers several benefits. It allows them to direct part of their tax payments to visible projects in the areas where they operate, which can improve relations with local communities.

The company effectively finances the project in advance and recovers the money later through tax credits. That means it bears the cost of capital during construction and must manage execution risk.

For governments, the main advantage is speed. Private firms often execute projects faster than public entities, which face complex procurement rules and limited technical staff.

Critics raise several concerns. Companies may favour projects that benefit their operations, such as roads near mines. Costs may be higher than in a competitive public tender. Oversight may be weaker if public entities lack the capacity to supervise.

Supporters respond that the mechanism includes supervision requirements and that the alternative, in many cases, is that projects are not built at all.

The fiscal impact is important. Since companies pay for projects through tax credits, the government receives less tax revenue in later years. The mechanism therefore changes the timing and control of spending rather than creating new money.

For students, the case shows how tax policy can be used as an investment tool and how it shifts both responsibility and risk between the public and private sectors.

Growing use of the mechanism has made it a significant part of public investment in many regions.

Transparent reporting by the Ministry of Economy and Finance and ProInversión allows the public to follow which projects are awarded, who finances them and how far they have progressed.

That transparency is essential for maintaining public trust in a mechanism that links private companies so closely to public spending.

As the volume of projects grows, the quality of supervision by public entities will be increasingly important.

Independent evaluations of completed works would help show whether the mechanism delivers better value than conventional public procurement.

02 · Timeline

Key moments

  1. Law 29230 established the Obras por Impuestos framework.

  2. Official guidance explains certification of eligible advances against tax obligations.

03 · Exhibit
Exhibit 1 · Obras por Impuestos awards by year
S/ millionS/4,203m2024S/5,180m2025

Sources: ProInversión via Energiminas (2024); El Peruano (2025).

04 · Core tensions

The trade-offs at the heart of the case

A public project has more than one financing date

FOCAM transfers resource-linked income to public investment. Obras por Impuestos brings forward eligible spending in exchange for later tax value. In both cases the date a project is chosen may be well ahead of the date a particular party can spend or recover cash.

Our assessment

I would compare this route with ordinary procurement for the same asset, standard and completion date. Faster delivery can have public value that exceeds a modest financing cost. A project with unclear land access or unresolved design issues can instead leave both sides waiting. Publish dates of selection, certified work and credit use so that the gain from earlier public service can be compared with the real cost of financing it.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    Which event gives the business usable tax value?

  2. Q2

    Who bears the interim cost of a disputed variation?

  3. Q3

    How would you demonstrate earlier public service relative to regular procurement?

  4. Q4

    Would paying to accelerate construction recover a full year of receipts or only change their timing?

Frameworks worth applying
  • Tax credits
  • Public investment
  • Private participation
  • Local government finance
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

We think Obras por Impuestos is a practical way to speed up public investment in a country where many regional and local governments struggle to spend their budgets. It works best when projects are well chosen and closely monitored.

  1. Prioritise needs

    Choose projects that close real service gaps.

  2. Monitor quality

    Inspect works independently.

  3. Publish data

    Report costs and outcomes for each project.

What this plan gives up

Private execution speeds projects but can blur accountability.

The strongest counter-argument

Critics argue companies may choose projects that suit their own interests.

Metrics to watch

  • Projects completed on time
  • Cost overruns
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.