What happened
A fleet can be ready at one end of a contract while the power supply it was meant to use is missing at the other. The Great Western modernisation linked decisions about new trains to decisions about overhead lines. As costs increased, ministers had a choice beyond simply approving a bigger construction budget. Trains able to operate on more than one source of power could deliver some passenger benefits before the entire route was wired. The financial issue was which sections still justified electrification and when.
For a section used intensively, electrical operation can spread infrastructure cost over many train movements. A lightly used branch has a different calculation. The marginal section may also eliminate a need to use diesel elsewhere or simplify fleet movements, giving it value beyond its own passenger count. Deferral changes both capital spending and the running costs of the train fleet. The two budgets belong to different organisations, so a saving reported by one can reappear as a cost for the other.
The NAO reported a revised £2.8 billion estimate, £1.2 billion above the 2014 estimate. Subtraction implies an earlier estimate of £1.6 billion. The rise relative to that base is about 75%. It is not a forecast increase for every remaining section. Some work may have proved unusually difficult because of clearances, access or sequencing. An informed decision requires the remaining cost to wire a particular stretch, even if the entire programme has already exceeded its budget.
The review reported that electrification delay could cost the department up to £330 million. That figure had a different scope from the rise in the infrastructure cost estimate. A finance director should identify the extra costs incurred by train and service arrangements and check whether any have already been recognised elsewhere. The public sector’s total exposure can be hidden at the boundary between infrastructure and train procurement, yet simply adding upper estimates without reconciliation can produce the opposite error.
Trace one actual service diagram from depot to destination and back again. Record the traction available at each point, the maintenance implications of carrying two systems and the journey time if power changes on the way. Repeat for a second diagram that uses the line less frequently. The two diagrams may give the same section of overhead wire very different economic significance. A decision based solely on track length ignores this variation. The sponsor should also examine planned works requiring the track to close anyway. Coordinating installation with a future closure can make deferral valuable, whereas missing an unusually favourable access window can make an apparently cheap postponement costly.
In January 2013 Network Rail estimated that electrifying the Great Western line between London Paddington and Cardiff would cost £874 million. By September 2014, after a single delivery option had been chosen, the estimate for Maidenhead to Cardiff was £1,529 million. In October 2015 Network Rail’s chief executive, Mark Carne, told MPs the cost could reach £2.5–2.8 billion.
The National Audit Office’s November 2016 report called it a case study in how not to manage a major programme. It found that electrification between Maidenhead and Cardiff was expected to cost £2.8 billion, 70% more than the 2014 estimate, and that the wider modernisation programme had risen by £2.1 billion since 2013 to £5.58 billion. Delays of at least 18 to 36 months could cost the Department for Transport up to £330 million. Network Rail had not surveyed the locations for some structures in enough detail, so design work had to be repeated.
The NAO estimated that the benefit–cost ratio had fallen from 2.4:1, expected in March 2015, to 1.6:1. In November 2016 the government deferred several sections, including Oxford, Bath and Bristol, saving about £150 million. Hitachi’s new Intercity Express Trains, which can run on electricity or diesel, made that choice possible.
Key moments
Network Rail estimates the electrification cost on an earlier timetable.
The programme is replanned as costs and dates move.
The department announces deferrals on some sections.
The 2013 figure covers London–Cardiff; the 2014 and later figures cover Maidenhead–Cardiff. Sources: NAO (2015, 2016); Rail Magazine.
The trade-offs at the heart of the case
A comparison with Edinburgh Trams: Redrawing the project after costs have changed
Edinburgh could buy a shorter usable tram line. The Great Western programme could defer some wiring and rely on rolling stock able to operate across gaps. Both options changed what the original system would deliver. A smaller project can be sensible even if the original project was a mistake, and it can destroy value if it removes a connection essential to the remaining assets. Draw the revised network from the user’s perspective. For a tram passenger, the value of the revised terminus depends on walking distance, interchange and onward frequency. For a railway operator, the value of an electrified stretch depends on which vehicles can use it and what happens when they reach the end of the wires. A map of completed engineering works alone would mislead both investors. Next price the practical option to extend later. Keeping land accessible or designing a junction for future construction may be cheap today and valuable later. Keeping an entire workforce or costly equipment available indefinitely can be much more expensive. Decide which options have an identifiable exercise date or trigger. Managers can then distinguish purposeful staging from an unresolved commitment that continues to consume resources without ever facing a fresh decision.
What to watch
The owner of a complementary asset needs more than a contractor’s completion date. A vehicle is productive only if the infrastructure, staffing and timetable make it usable. Ask what can be salvaged from a partly complete system, which parts can operate independently and what it costs to keep the future option open. A deferred project with a deliberate protection plan is economically different from an abandoned project, even when both show zero construction expenditure in the next annual budget.
For your seminar, paper or interview
- Q1
Which section should be wired first if only one can proceed?
- Q2
When does the operating flexibility of a bi-mode train cease to cover its extra lifetime cost?
- Cost estimating
- Optimism bias
- Real options
- Benefit–cost ratio
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
Buy bi-mode trains
Use trains that run on wires or diesel so service could improve before wiring finished.
Defer marginal sections
Postpone electrification to Oxford, Bath and Bristol Temple Meads branches.
Re-plan the programme
Reset the baseline with more realistic costs and dates.
What this plan gives up
Deferring sections saved money and used the flexibility of bi-mode trains, but it left passengers with diesel running and weakened the case for a fully electric network.
The strongest counter-argument
Selective electrification can leave short unwired gaps that make the fleet permanently more complex. Carrying two forms of propulsion has a cost even on a fully wired section. A route-wide solution can win when it allows the operator to simplify maintenance or retire a class of equipment.
Metrics to watch
- Cost per kilometre of electrification
- Benefit–cost ratios on new schemes
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- National Audit Office: Modernising the Great Western railway ↗
- Department for Transport: Great Western route investment statement ↗
- Accounts Commission: Edinburgh tram project reporting ↗
- NAO: Modernising the Great Western railway (2016) ↗
- NAO: Modernising the Great Western railway, summary ↗
- NAO: Planning and delivery of the 2014–2019 rail investment programme ↗
- Rail Magazine: Great Western costs soar to £2.8 billion ↗
- Railnews: Audit Office calls for Great Western rethink ↗
- Image: AI-generated editorial illustration
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.