What happened
On a fixed-price (lump-sum) contract, the contractor promises a price before knowing every cost. When labour, materials or designs change, the contractor absorbs the overrun. Several such contracts drove Fluor into heavy losses.
Its new model relies on reimbursable contracts, where clients pay actual costs plus a fee. Margins are lower but more predictable. Legacy disputes still produce surprises, such as a large court ruling in 2025.
The lessonIn construction, the contract type can matter more than the engineering. Taking on risk you cannot price is not a strategy.
Key moments
John Simon Fluor founds a construction business in California.
Fluor wins large fixed-price projects at thin margins.
Big charges on problem projects; the dividend is suspended and the strategy reset.
Fluor shifts to reimbursable contracts and sells non-core units.
It sells its stake in nuclear company NuScale and buys back shares.
For your seminar, paper or interview
- Q1
Why do contractors accept fixed-price contracts?
- Q2
What are the trade-offs of reimbursable contracts for Fluor and its clients?
- Q3
Was selling the NuScale stake a good decision?
- Risk allocation in contracts
- Winner’s curse in bidding
- Capital allocation
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- Fluor: Q4 and full-year 2025 results ↗
- Panabee: NuScale monetisation and reimbursable backlog ↗
- Construction Dive: legacy fixed-price exposure ↗
Figures are as reported in the cited sources. Check the source before quoting. Corrections: let us know through the solution form.