What happened
The AP1000 was a new design built with new supply chains and a workforce that had not built reactors for decades. Designs were changed during construction, modules arrived late or faulty, and costs multiplied. Westinghouse had agreed to fixed-price terms and could not absorb the losses.
Vogtle units 3 and 4 were eventually completed, years late and far over budget. That experience — a trained workforce and a proven design — is why governments now see the AP1000 as a basis for new reactors, this time with state financial support.
The lessonFirst-of-a-kind projects are very hard to price. Fixed-price contracts on new technology can destroy even large companies.
Key moments
Toshiba buys Westinghouse at a high price, betting on a nuclear renaissance.
Construction starts on two new AP1000 reactors each at Vogtle (Georgia) and VC Summer (South Carolina).
Cost overruns trigger bankruptcy; VC Summer is abandoned; Toshiba records huge losses.
Brookfield buys Westinghouse; later Cameco takes 49%. Vogtle’s new reactors finally start in 2023–2024.
The US government agrees to back at least $80bn of new Westinghouse reactors.
For your seminar, paper or interview
- Q1
Why did the AP1000 projects overrun so badly?
- Q2
Who should bear the cost of first-of-a-kind infrastructure?
- Q3
Is government backing of new reactors a good use of public money?
- First-of-a-kind risk
- Learning curves
- Industrial policy
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- EnergyTech: $9bn losses and bankruptcy ↗
- S&P Global: the $80bn partnership ↗
- NEI Magazine: US government signs Westinghouse plan ↗
Figures are as reported in the cited sources. Check the source before quoting. Corrections: let us know through the solution form.