Lendlease and Consigli

Selling a construction backlog one contract at a time

A builder can sell a business, but its clients may still have to accept the new party responsible for finishing their buildings. That makes a backlog a complicated asset to transfer.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Approximate projects in announced scope45
Target disposal window18 months
Group strategy update27 May
Terms announced29 May
01 · The situation

What happened

On 29 May 2024 Lendlease announced agreed terms with Consigli for its US East Coast construction operations, subject to due diligence and final documentation. About 45 current, contracted and pre-construction projects were included in the description. Lendlease had just outlined a target to divest US and UK construction businesses over 18 months. The announcement describes the proposed transaction at that point. A project in pre-construction is a different commercial commitment from a building already under contract.

A backlog is often quoted as revenue to be earned, not profit secured. Margins can change with subcontractor pricing, design revisions, delay claims and the ability to recover variations from the client. Project knowledge also lives with the staff who priced the work. If key managers leave between signing and transfer, the successor can inherit both an expensive promise and an incomplete account of why it was made.

In May 2024 Lendlease announced a strategy reset to focus on Australia and sell its international construction businesses in the US and UK over 18 months, as part of a plan to release up to about A$4.5 billion of capital. On 29 May 2024 it said it had agreed terms to sell its US East Coast construction operations to Consigli Construction, subject to due diligence and documentation.

The business included about 45 current, under-contract and pre-construction projects in New York and New Jersey. Lendlease had worked on landmark projects there, including the National September 11 Memorial & Museum and Central Park Tower. A binding agreement followed: the consideration was a profit share and earn-out payable two years after completion, and more than 400 people, about 90% of Lendlease’s US construction staff, would move to Consigli.

The sale completed in September 2024. Consigli said the portfolio of work was valued at over US$1.8 billion. Lendlease said the decision would lead to an impairment of related goodwill and deferred tax assets.

Construction margins are thin and risks are high. The case shows how earn-outs can bridge gaps between buyers and sellers when the value of a contract backlog is uncertain.

02 · Timeline

Key moments

  1. Group sets divestment direction

  2. Terms with Consigli announced

  3. Due diligence and final documents still required

03 · Exhibit
Exhibit 1 · Lendlease’s US East Coast construction sale
Value45Projects transferred (count)4Staff moving to Consigli (hundreds)18Work portfolio (US$ hundred million)

About 45 projects with a portfolio of work valued at over US$1.8bn; more than 400 staff (about 90% of Lendlease’s US construction employees). Consideration was a profit share and earn-out payable two years after completion. Sources: Consigli; Australian Property Journal; Construction Dive.

04 · Core tensions

The trade-offs at the heart of the case

Backlog moves only as fast as the client consents

A profitable project on paper may require client approval before a new contractor can invoice it. A contract may transfer while an old performance guarantee remains outstanding. A manager who negotiated a verbal understanding on a variation may leave before the successor can document it. Each issue belongs in a separate closing checklist with a named decision maker. The seller wants to leave only when its exposure ends. The buyer wants control only when it can actually direct subcontractors. Matching those dates contract by contract can matter more to economic value than the nominal enterprise sale price. The new owner may have better subcontractor relationships in a local market or a lower overhead base. That can turn a marginal job into an attractive one without implying that the seller mismanaged it. Conversely, expected savings cannot be applied to contracts where subcontractors are already fixed and the customer retains the benefit of cost improvements. Read the contract type before assigning synergy value. The most profitable transferred job may be the one whose client and team stay together through delivery.

Testing the evidence

To investigate the claim empirically, define a consistent unit of observation. Compare projects successfully transferred with their teams with comparable projects with incomplete client consents, using remaining margin after claims and completion costs as the principal measure. Document project stage and fixed-price exposure before examining the result. Otherwise a researcher could select whichever adjustment makes the original recommendation look strongest. Report how many observations drop out and whether missing records cluster around difficult operating periods. Use client novations matched to bond releases and forecast completion costs to reconstruct the decision as it looked at the time. Keep subsequent information in a separate column. Hindsight can establish what eventually occurred, but it cannot establish that a manager could have known it with reasonable confidence beforehand.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    Which single incomplete contract would you most want to exclude from a headline measure of risk transferred?

  2. Q2

    How would you use comparable projects with incomplete client consents to test changes in remaining margin after claims and completion costs, while allowing for project stage and fixed-price exposure?

  3. Q3

    Compare the recommended course with letting selected projects run off before selling the remainder of the operation. Which commitment would you make first, and what result would cause you to change course?

Frameworks worth applying
  • Strategic retreat
  • Earn-out structures
  • Construction risk
  • Portfolio simplification
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

Make closing tests project-specific. Reconcile cost to complete, client approval, subcontractor commitments and the treatment of warranties before counting a contract as transferred. Report the reduction in retained risk alongside any proceeds. Removing a spectacular revenue backlog can strengthen shareholders’ position if the most fragile estimated margins went with it.

  1. Sell the platform with its people

    Transfer staff and projects together so clients see continuity.

  2. Use an earn-out

    Accept payment tied to future profits to bridge valuation gaps.

  3. Focus on the home market

    Concentrate capital on Australian investment and development.

What this plan gives up

Selling the US construction business reduced Lendlease’s risk and freed management attention, but the payment depended on future profits, and exiting meant writing off goodwill.

The strongest counter-argument

Allowing selected contracts to run off would preserve knowledge and avoid transferring disputed obligations. It would also keep overhead, guarantees and regional management in place for longer. Classify the projects by how safely their obligations can travel. A mixed strategy may beat either an immediate transfer of everything or a prolonged full-scale exit. In construction, collecting a progress payment may have been easy because the client trusted a particular project director. Moving that director to another employer can preserve the relationship, provided the team, reporting and responsibility move with the person. A sale of nominal contracts without that continuity could increase disputes about earlier work. A prudent buyer examines outstanding claims with the client and makes its own estimate of future cost rather than relying entirely on the seller’s percentage-complete accounting. Include cash owed to subcontractors and the client’s right to withhold payment. Moving the contract between owners does not resolve a disagreement over whether the work meets specification.

Metrics to watch

  • Earn-out payments
  • Progress on UK construction sale
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.