What happened
Cement is valuable to a construction site and expensive to transport relative to its value per tonne. A plant with a modern kiln can improve conversion economics while remaining exposed to the geography of building activity. Loma Negra described its second L’Amalí line as a large capacity addition. The question for an investor was how many extra tonnes the company could place at a positive delivered margin without displacing profitable shipments from its own other facilities.
Bulk cement and bagged cement can travel through different routes even when both originate at the same plant. A distant customer may justify a trainload because it offers steady orders and rapid unloading. A closer customer receiving small, irregular deliveries could cost more to serve per tonne. Distance is therefore a starting point for calculating the sales radius rather than the final answer. Include handling, minimum order size, trip utilisation and the cost of returning vehicles empty. A plant with spare kiln capacity can remain constrained by those downstream resources. Expanding its effective market may require a distribution investment instead of another improvement to production.
US$350 million divided by 2.7 million tonnes of added annual capacity gives roughly US$130 per annual tonne of capacity. That is a measure of capital intensity, not the cost of making a tonne or its selling price. The cited 40% company capacity increase is likewise different from a 40% rise in sales or a 40% improvement in profit.
Loma Negra is Argentina’s largest cement maker. It has been part of the InterCement group, controlled by Brazil’s Camargo Corrêa, since 2005, and its shares trade in Buenos Aires and New York. Its L’Amalí plant in Olavarría, Buenos Aires province, is its most modern site.
In 2017 it contracted China’s Sinoma to build a second L’Amalí line, adding 2.7 million tonnes a year for about US$350 million. Work slowed during pandemic lockdowns. The new kiln was ignited in June 2021, expanding the plant’s capacity by 40%, and the line was formally inaugurated later in 2021 with Buenos Aires governor Axel Kicillof, who said the investment made it the most important cement plant in South America.
In 2020 Loma Negra sold its controlling stake in Paraguay’s Yguazú Cementos for US$107 million, using the money mainly to repay debt and pay an extraordinary dividend. The case shows why cement capacity is only valuable where trucks and trains can reach customers cheaply.
Key moments
Construction begins on the second L’Amalí line.
Work is interrupted during isolation measures.
Loma Negra inaugurates the expanded Olavarría plant.
The new line added 2.7 million tonnes a year, about 40% more capacity. Proceeds from Paraguay were used mainly to repay debt and pay an extraordinary dividend. Sources: Loma Negra 20-F; Global Cement.
The trade-offs at the heart of the case
Core tensions
A plant can raise its own utilisation by shipping into a neighbouring plant’s market. Group utilisation and cash generation may improve much less. Extending the sales radius can also require rail or road capacity, more working capital and longer customer lead times. Those costs belong in the comparison of an extra sale with its best alternative source. Turning down a distant order can be rational even with spare capacity if serving it consumes a scarce transport slot required by a better customer. Conversely a temporary discounted order can help maintain a rail service that lowers cost on the rest of the network.
Testing the evidence
The appropriate unit of observation is one tonne delivered to a defined market. Track contribution after freight and displaced internal volume and record the baseline before the decision. The most useful records are dispatch records, customer locations and route-level freight costs. Align their dates and definitions before drawing an inference. In particular, allow for construction cycles and changes in transport tariffs. A change in that factor can move the reported outcome even when the intervention has had no effect. Follow orders by delivery site and source plant. Compare total group margin before and after routing changes, adjusting for transport tariffs. A fully utilised new line accompanied by a newly idle neighbouring plant requires an explanation at network level.
A related Argentine case
For Rosario crushers, freight changes the price of getting a bean into the plant. For Loma Negra it changes the margin left after a tonne arrives at the construction site. Both decisions belong at the delivered-cost boundary.
For your seminar, paper or interview
- Q1
Which additional tonne would look profitable at the factory gate and lose money at the customer’s site?
- Q2
How would you measure contribution after freight and displaced internal volume for one tonne delivered to a defined market using the available records?
- Q3
Which assumption in “Which customer is worth the freight?” would you challenge first, and how would changing it affect the decision?
- Q4
Could construction cycles and changes in transport tariffs explain the observed change? What evidence would distinguish that explanation?
- Q5
Under what conditions would you prefer redistributing existing production before extending the delivery radius, and who would bear the residual risk?
- Capacity expansion
- Transport costs and market reach
- Cyclical demand
- Portfolio choices
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
Map each destination to its lowest delivered-cost plant under realistic transport constraints. Prioritise incremental sales and cost-saving transfers separately. Treat the new line as insurance against old-plant downtime only where dispatch and inventory arrangements make that insurance usable.
Expand at the best plant
Add a second line at L’Amalí in Olavarría.
Keep building through the pandemic
Resume construction after lockdown interruptions.
Sell a non-core unit
Exit Paraguay and use the cash to cut debt.
What this plan gives up
New capacity lowers unit costs and prepares for future demand, but cement is cyclical and costly to transport, so extra tonnes are only valuable if nearby construction grows.
The strongest counter-argument
For the cement network planning team, the alternative worth costing is redistributing existing production before extending the delivery radius. Give both choices the same information date. Specify what can still be reversed, who absorbs the cost if the forecast is wrong, and the point at which new evidence would justify changing course. Make the decision conditional on an observable change in contribution after freight and displaced internal volume. That condition lets someone outside the original decision team distinguish a sensible revision of the plan from an attempt to explain away poor results.
Metrics to watch
- Cement dispatches in Argentina
- Loma Negra margins
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- Loma Negra: Sustainability report, L’Amalí second line ↗
- Buenos Aires Province: Q2 2021 investment announcements, added capacity and construction chronology ↗
- Global Cement: Loma Negra launches production at expanded L’Amalí ↗
- Loma Negra: Form 20-F 2020 ↗
- Province of Buenos Aires: Kicillof at the inauguration of the new line ↗
- Mercado: Loma Negra inaugura una nueva línea ↗
- Image: AI-generated editorial illustration
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.