What happened
The JENDELA Phase 1 closing report lists targets for 2020–2022 of 96.9 percent 4G coverage in populated areas, 7.5 million premises passed for gigabit service and a 35 Mbps mobile broadband speed measure. Bernama reported figures from the communications regulator of 96.92 percent populated-area coverage and 7.74 million premises at the close of the phase. Separate the mobile coverage measure from fixed-network premises passed. Neither is a direct count of households with affordable subscriptions.
The closing report gives the first phase a defined interval from September 2020 through December 2022. The later announcement reported performance against that programme baseline.
JENDELA, the National Digital Network Plan, was launched in 2020 to improve internet access across Malaysia, especially outside major cities. Phase 1 ran from September 2020 to December 2022. Its targets were 96.9 percent 4G coverage of populated areas, 7.5 million premises passed with gigabit-capable fibre, and average mobile speeds of 35 Mbps. At the start, 4G covered about 91.8 percent of populated areas and fibre passed about 4.96 million premises.
Phase 1 exceeded all three targets. The communications regulator, MCMC, reported 96.92 percent 4G coverage, 7.74 million premises passed with fibre and average mobile broadband speeds of about 116 Mbps. It also completed 839 satellite broadband sites in remote areas, and shutting down the 3G network allowed its spectrum to be reused for 4G. Analysts put the cost of Phase 1 at about RM28 billion, with roughly 40 percent borne by the government; network complaints fell by about two-thirds in 2022.
Phase 2, from 2023 to 2025, aims for 100 percent internet coverage of populated areas, 9 million fibre premises and 100 Mbps mobile speeds. The remaining gaps are the hardest and most expensive: remote villages, interior Sabah and Sarawak, and places with difficult terrain where each new connection costs far more.
Key moments
JENDELA announced
Phase 1 begins
3G network shut down; spectrum reused for 4G
Phase 1 ends, exceeding its targets
Phase 2 targets 100 percent coverage and 9 million fibre premises
Average mobile broadband speed reached 116 Mbps against a 35 Mbps target. Sources: MCMC; SoyaCincau; The Vibes.
The trade-offs at the heart of the case
Find the denominator that matters to a village
A national percentage gives more weight to places with many people. It can improve most cheaply through service at the edges of towns. A road to a clinic or a remote settlement may matter intensely to residents while barely moving the national measure. The finance committee should compare the cost of each candidate site with independently verified outcomes in its actual catchment and the availability of alternatives.
Use one community to audit the headline
Ask a clinic, a shop and a household in the same rural catchment to perform their ordinary tasks at a busy hour. Their different results can identify a missing link in power, backhaul, equipment or affordability. Compare those observations with the programme’s definition of coverage before funding another tower. This preserves a national metric useful for coordination while making clear which expensive local problems the next phase must solve and which would survive another increase in the reported percentage.
For your seminar, paper or interview
- Q1
Which households are missing from a national coverage metric?
- Q2
What would you pay for service uptime at a clinic?
- Q3
Where could affordability matter more than radio coverage?
- Q4
Which tests would reveal intermittent service in a counted area?
- Q5
How should a tender handle repairs during difficult travel conditions?
- Universal service
- Measuring coverage
- Last-mile economics
- Public investment targets
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
JENDELA Phase 1 shows the value of clear, measurable targets: coverage, fibre and speed all improved beyond plan in just over two years. The harder test is the last few percent, where costs per household rise sharply.
Measure at village level
Track coverage and speed by locality, not just nationally.
Target the last mile
Use satellite and shared infrastructure for remote sites.
Address affordability
Pair coverage with low-cost plans and devices.
What this plan gives up
Chasing 100 percent coverage improves inclusion but at rapidly rising cost per new user.
The strongest counter-argument
A national percentage can hide large gaps in specific villages, and coverage does not guarantee affordable or reliable service. Public spending on the final few percent may deliver less benefit per ringgit than other priorities.
Metrics to watch
- Progress on JENDELA Phase 2 targets
- Rural broadband prices and usage
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- JENDELA: Phase 1 concluding report ↗
- Bernama: regulator reports first-phase JENDELA results ↗
- MCMC: JENDELA Phase 1 concluding report ↗
- SoyaCincau: JENDELA Phase 1 final report ↗
- Business Today: JENDELA, the next phase ↗
- The Vibes: JENDELA Phase 1 surpasses targets ↗
- Image: Tombongon village in Sabah illustrates the rural connectivity question. Photograph: CEphoto, Uwe Aranas, CC BY-SA 3.0 (cropped and resized) ↗
Figures are as reported by the companies or cited outlets as of 25 November 2026. Check the source before quoting. Corrections: let us know through the solution form.