What happened
A congressional inspection report describes PROVISUR’s desalination plant at San Bartolo, a reported flow of 400 litres per second and service to Punta Hermosa, Punta Negra, San Bartolo and Santa María del Mar. If that flow were sustained continuously for one day it would equal 34,560 cubic metres. That is a unit conversion. It is not evidence of actual production, customer consumption or billed supply on the inspection date.
Follow water through five separate measurements. The plant produces water, the network receives it, customer meters register consumption, a utility issues bills and customers pay them. Leaks and operating downtime affect physical quantities. Tariffs, payment terms, collection delays and the structure of the service contract affect cash. Decide who pays the energy cost when output rises and what happens to fixed costs in low-demand months. A contractual availability payment can change which party bears seasonal demand risk.
A summer surge can occur across all four coastal districts at once. A supply design that relies on spare capacity in a neighbouring district may therefore be less useful than a calculation using independent demand peaks suggests. Compare hourly or daily peaks across the service area and identify any network bottleneck between the plant and each district. An interruption at the plant intake affects several districts differently from a local network leak. A service-level contract should recognise the distinction. To assess how a resident benefits, examine hours of dependable service and the cost of emergency alternatives as well as the official tariff. Insurers, operators, customers and the public budget can each bear a different share of the same period of water scarcity.
Lima is one of the largest cities in the world built in a desert. It receives very little rain and depends mainly on rivers fed by Andean rainfall and glaciers, such as the Rímac, Chillón and Lurín.
The southern coastal districts of Punta Hermosa, Punta Negra, San Bartolo and Santa María del Mar have grown as beach and residential areas, but many homes have historically lacked a reliable connection to the city water network.
PROVISUR, a public-private partnership project for the southern Lima sanitation service, built a desalination plant to supply these districts. A congressional inspection on 2 December 2022 described the plant at San Bartolo with a reported flow of 400 litres per second.
Desalination removes salt from seawater, usually through reverse osmosis, which forces water through membranes at high pressure. The process uses large amounts of energy, which makes up a major share of operating costs.
A flow of 400 litres per second is equal to 34,560 cubic metres per day, a simple conversion that helps compare the plant with other water sources.
Utilities must decide whether to invest in desalination, new dams, reduction of leaks or reuse of treated wastewater. Each option has different capital costs, operating costs and risks.
Countries with scarce water, from Israel to Spain and Chile, rely increasingly on desalination, especially for coastal cities.
For students, the case shows the difference between capital and operating costs in infrastructure, and why the cost per unit delivered is the key measure for comparing projects.
Before the plant, many households in these districts relied on water delivered by tanker trucks, which is usually much more expensive per litre than piped water and less reliable.
The plant’s value depends on how much of its capacity is used and whether the distribution network can deliver water to homes. A plant producing water that cannot reach customers creates costs without benefits.
Seasonal demand is a particular challenge. The beach districts have much higher populations in summer, when visitors and holiday residents arrive, so capacity must be sized for peak periods.
Pricing is also important. If tariffs do not cover operating costs, the utility or the government must subsidise the service. If tariffs are too high, households may struggle to pay.
Reliable data on actual output and delivery are therefore essential for judging whether the plant represents good value.
Comparing those figures with tanker costs gives a clear benchmark for households.
Those comparisons should be published regularly, so residents can see what they receive.
Key moments
PROVISUR was designed to serve four districts on Lima’s southern coast.
A congressional committee inspected the San Bartolo desalination facilities.
Source: congressional inspection report cited in the case.
The trade-offs at the heart of the case
Who pays for a dependable water supply?
La Enlozada connects a city’s wastewater to industrial demand. PROVISUR treats seawater for coastal households. Both appraisals improve when they follow a measured cubic metre through treatment, delivery and payment, then assign the public benefit separately from contractual revenue.
Our assessment
I would compare the system with its feasible alternatives on the same delivered-service basis, including reliability during peak weeks. A low unit cost at full utilisation can conceal high costs in quieter months. An incremental plant may still be worthwhile if it avoids particularly expensive shortages. Put the value of dependable supply beside the financial return of the operator, identifying the source of payment in each case.
For your seminar, paper or interview
- Q1
Why does 34,560 cubic metres per day differ from billable water?
- Q2
Who bears the cost of low-season spare capacity?
- Q3
How would you value supply available only when other sources are scarce?
- Q4
Which observations would verify demand at the time and location the capacity is available?
- Q5
Would a smaller fixed commitment or a guaranteed unit margin give better downside protection?
- Water infrastructure
- Desalination
- Public-private partnerships
- Utility pricing
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
We think desalination is an important option for Lima’s southern beach districts, which lack reliable fresh water. But its high energy and operating costs mean it must be planned as part of a wider water strategy, not as a quick fix.
Track costs
Measure cost per cubic metre delivered.
Plan capacity
Match supply to seasonal demand.
Use energy efficiently
Reduce the main cost of desalination.
What this plan gives up
Desalination provides secure supply but at high cost.
The strongest counter-argument
Some argue reducing leakage and reusing water would be cheaper.
Metrics to watch
- Plant utilisation
- Cost per cubic metre
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- Congress of Peru — Housing committee management report, 2022–2023, PROVISUR inspection ↗
- Ministry of Housing — PROVISUR environmental and project documentation ↗
- Photo: Santa María del Mar 2 by Manuel González Olaechea y Franco, CC BY-SA 3.0 (cropped and resized) ↗
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.