Case study · PakistanCapital budgetingJune 2024Last reviewed 22 November 2026

Pakistan case studiesAsia-Pacific case studies

Dasu Hydropower Stage I

Another billion dollars at Dasu

Once substantial money has gone into a megaproject, stopping can look like admitting that the original decision was wrong. Continuing can also be wrong. The correct comparison starts with the costs and options still open today.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Stage I capacity2,160 MW
Additional financingUS$1 billion
Estimated economic returnAbout 28 percent
01 · The situation

What happened

On 10 June 2024 the World Bank approved US$1 billion in a second round of additional financing for Dasu Hydropower Stage I. The stage is designed as a 2,160 MW run-of-river project. The financing announcement described money approved to advance the project. It did not announce that the capacity was already delivering electricity or that the amount approved represented the total construction cost.

A partially built project has assets that can be used only if other works finish. Money already spent is sunk, but the remaining physical works have genuine option value. So do unavoidable obligations to communities and contractors. An appraisal of stopping that enters no future costs can be just as misleading as an appraisal of continuing that counts every past expense as a future benefit.

The Dasu Hydropower Project is a run-of-river plant on the Indus in Upper Kohistan, Khyber Pakhtunkhwa. It is being built in stages: Stage I has 2,160 MW and is expected to produce about 12,225 GWh a year, while later stages could raise capacity to 4,320–5,400 MW. The World Bank calls the site one of the best hydropower sites in the world.

On 10 June 2024 the World Bank approved US$1 billion in a second round of additional financing, bringing its support to about US$1.7 billion for a Stage I project that Dawn reported would cost about US$2.5 billion. The Bank estimated the project could save Pakistan US$1.8 billion a year in imported fuels, offset about 5 million tonnes of carbon dioxide and earn an economic return of around 28 percent. A separate US$700 million was approved in 2020 for a 250 km transmission line.

The project has faced delays from land acquisition, resettlement and security; in 2021 a bus carrying Chinese engineers to the site was attacked. The World Bank has highlighted social benefits in the area, including increases in adult literacy and girls’ schooling. Generation from Stage I was expected to begin around 2026.

02 · Timeline

Key moments

  1. World Bank approves original financing

  2. US$700 million approved for transmission line

  3. US$1 billion second additional financing approved

  4. First generation expected

03 · Exhibit
Exhibit 1 · Dasu Hydropower Stage I
as stated2,160.0Stage I capacity (MW)12,225.0Expected annual output (GWh)1,000.0World Bank additional financing, 2024 (US$ m)1.7World Bank total after 2024 (US$ bn)

Dawn put the Stage I cost at about US$2.5 billion; full build-out 4,320–5,400 MW. Sources: World Bank; Dawn.

04 · Core tensions

The trade-offs at the heart of the case

Core tensions

Additional finance can preserve construction momentum and prevent costly demobilisation. Releasing it without a believable plan for critical works can increase exposure while pushing the first meaningful operating return further away. Delays also have consequences for the system, which must procure replacement electricity. Those savings belong in the model only from the time the project can actually export.

The community whose move sets the schedule

A project team can complete a large share of excavation and still be unable to use the next site until an access or resettlement commitment is fulfilled. Expenditure is then a misleading measure of progress along the critical path. A social commitment has independent value for the people affected and can also govern financing risk because work cannot safely or legitimately proceed without it. An engineer estimating remaining costs should include the price of maintaining partially completed works during delay. A funding package can make continuation feasible without making its underlying social return attractive. Equally, a project can have a strong social return and face an unfinanceable gap between costs and receipts. Keep the economic comparison and the treasury plan side by side when deciding what an additional loan can change.

What an additional financing approval changes

More money can allow an essential contract to proceed. It does not move the first date of commercial generation if another unfinished package still determines that date. The relevant question at an additional financing decision is which dependencies the money resolves, how much delay remains and whether the value of finishing exceeds the remaining cost under a realistic schedule. Prepare two versions of the completion plan. In the first, the extra funding is available on the anticipated dates and enables the critical works. In the second, a package with no funding shortage is delayed by site conditions. The difference shows how much economic value depends on the financing itself and how much depends on resolving a separate constraint. Money already spent gives stakeholders a strong reason to seek a workable solution. It should enter the decision only through its effect on remaining alternatives, such as the value of partially completed assets, contractual termination costs or a cheaper route to completion.

More money, same deadline

Additional financing keeps contractors working and avoids the cost of stopping and restarting. But it does not by itself solve the problems that caused delays, such as land acquisition and resettlement. Lenders must ensure that new money comes with a credible plan to address them.

Communities set the pace

A dam cannot be completed until people living on the site have moved and been compensated. Resettlement that is rushed or unfair can lead to protests and further delays; resettlement done well takes time and money but makes the schedule more reliable.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    Which liability would persist even if construction stopped tomorrow?

  2. Q2

    How much value disappears when the first export of power moves back one year?

  3. Q3

    Which unfinished package sets the earliest date when Dasu can earn revenue?

Frameworks worth applying
  • Large project overruns
  • Additional financing
  • Resettlement
  • Economic returns
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

Dasu’s economics remain strong even with cost increases, because cheap hydropower replaces expensive imported fuel. The World Bank should tie further disbursements to clear milestones on resettlement and security, which drive the schedule.

  1. Link money to milestones

    Release funds as key obstacles are cleared.

  2. Invest in resettlement

    Treat community moves as critical path work.

  3. Report costs openly

    Publish updated estimates and reasons.

What this plan gives up

Continuing a large project avoids waste of sunk costs but risks further overruns.

The strongest counter-argument

Large dams have a long record of overruns; channelling more money into one project concentrates risk.

Metrics to watch

  • Date of first generation
  • Updated total cost
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.