Case study · PakistanRenewable power2013 commissioningLast reviewed 22 November 2026

Pakistan case studiesAsia-Pacific case studies

Zorlu Enerji Pakistan

How much electricity does 56.4 MW of wind buy?

A wind farm can be available to generate at a time when the wind is weak. It can also have strong wind when the grid cannot accept its output. An owner and a lender need to put those two shortfalls in different columns.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Capacity56.4 MW
Project costAbout US$143–159 million
CompletedMarch 2013
01 · The situation

What happened

Pakistan’s Private Power and Infrastructure Board lists Zorlu Enerji Pakistan’s Jhimpir wind project at 56.4 MW, with a commercial operation date of 26 July 2013. The rating is useful for identifying plant scale and for comparing the installation with others in the Sindh corridor. It does not report annual MWh delivered or money collected.

The mechanical upper bound in a non-leap year is 56.4 multiplied by 8,760 hours, or 494,064 MWh. Actual output must reflect the wind resource, technical availability, electrical losses and any restrictions on delivery. Some of these factors move together. For instance, a period of strong wind can be precisely when nearby farms are also producing and local transmission is heavily loaded.

The Zorlu Enerji wind farm at Jhimpir in Thatta district, Sindh, about 100–120 km from Karachi, was the first internationally financed wind power project in Pakistan. Turkish developer Zorlu installed a first phase of five 1.2 MW Vensys turbines, which began generating in April 2009, then added 28 Vestas turbines of 1.8 MW each, bringing capacity to 56.4 MW. The project was completed in March 2013.

The IFC, Asian Development Bank, ECO Trade and Development Bank and Habib Bank financed the project, whose cost was reported at about US$143–159 million. The Jhimpir corridor had been identified by the Alternative Energy Development Board and Pakistan Meteorological Department in 2005, with average wind speeds around 7.3 metres per second. Early projects received a ‘wind-risk’ guarantee that shielded them from below-forecast wind.

The farm sells its electricity at a tariff of about 12.1 US cents per kWh. Many more wind farms followed in Jhimpir and Gharo, including projects by China Three Gorges and others, using the grid connections and experience the first projects established.

02 · Timeline

Key moments

  1. Jhimpir wind corridor identified

  2. 6 MW phase I begins generating

  3. IFC, ADB and others finance phase II

  4. 56.4 MW project completed

03 · Exhibit
Exhibit 1 · Zorlu Enerji Pakistan wind farm
as stated56.40Capacity (MW)5.00Phase I turbines28.00Phase II turbines12.11Tariff (US cents/kWh)

Phase I: 5 × 1.2 MW Vensys; Phase II: 28 × 1.8 MW Vestas. Sources: Wikipedia; PPIB; IFC.

04 · Core tensions

The trade-offs at the heart of the case

Core tensions

A developer might buy more maintenance support to reduce unplanned outages. That investment has most value if the outages would otherwise coincide with windy hours when power could be exported. The same number of repairs scheduled during calm periods could have little effect on saleable output. An availability bonus based only on clock hours can therefore reward the wrong behaviour.

Where an availability warranty ends

A maintenance provider can warrant that a turbine is mechanically available without guaranteeing that the wind will blow or the buyer will accept electricity. If the owner seeks compensation after a weak production month, it must identify which risk the warranty actually covered. Maintenance expenditure and the price of insurance will be misvalued if the analyst silently assigns wind or grid risk to the service contractor. The cost of deferring an inspection should be expressed in expected MWh and expected repair expense, taking account of when the unit can be taken offline. A quiet period may offer a cheap maintenance window. Spare parts imported from abroad can change the calculation if a short repair becomes a long wait for delivery. Record the time between fault detection, spare availability and repair completion. Similar farms using the same turbines may report different performance because one maintains local inventory. That inventory ties up cash, which is part of the cost of achieving better availability.

A spare part on a windless day

A wind turbine that is unavailable for a day does not necessarily lose a day’s average electricity sales. A repair completed during calm weather may forgo little generation. The same failure during a windy period when the grid is accepting power can forgo much more. This gives a maintenance planner a different problem from a manager of a factory with uniform output per working hour. The price of a spare part should be compared with the energy it can realistically restore during the time it saves. Begin with a maintenance log showing when the original component failed and when the replacement arrived. Match those hours to local wind observations and export restrictions. Then consider whether the replacement would have been usable immediately or would also have required a crane, crew or permission to work. A spare stored on site is less valuable if that second constraint dominates the repair time. Conversely, a common spare shared across several compatible turbines can be valuable even when each individual machine has a low failure probability.

Available but not generating

A turbine can be mechanically available yet produce nothing on a windless day. Maintenance contracts usually guarantee availability, not output. Revenue depends on both, so the value of extra maintenance is highest during windy periods when an outage costs the most.

First mover costs

Pioneering projects pay for lessons later projects benefit from: grid connection, regulatory approvals, local logistics and tariff setting. Their tariffs are often higher than later projects, which can attract criticism even though they made the later ones possible.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    What would a 30% net capacity factor imply for annual MWh?

  2. Q2

    How should a maintenance bonus treat a turbine that is available through a calm week?

  3. Q3

    When is a spare component worth less than faster access to a repair crew?

Frameworks worth applying
  • Renewable project finance
  • Wind resource risk
  • Availability warranties
  • Development finance
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

Zorlu’s wind farm proved that international finance would back wind power in Pakistan. Its long-term value depends on keeping turbines available during the windiest months and on the grid absorbing its output.

  1. Focus maintenance on windy seasons

    Schedule repairs for calm periods.

  2. Keep spares close

    Stock critical parts locally to cut downtime.

  3. Share lessons

    Use first-project experience to lower later costs.

What this plan gives up

Early projects open a market but lock in higher tariffs.

The strongest counter-argument

High dollar-linked tariffs from early renewable projects have contributed to Pakistan’s expensive power purchase costs.

Metrics to watch

  • Capacity factor
  • Curtailment by the grid operator
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.