Case study · PakistanBrownfield infrastructure2020 project reviewLast reviewed 22 November 2026

Pakistan case studiesAsia-Pacific case studies

Tarbela Fourth Hydropower Extension

The turbine that uses a tunnel already there

At an existing reservoir, adding electricity generation can depend less on building a new dam than on what the water is already required to do. Tarbela’s fourth extension turned this into a question about the incremental value of an existing tunnel.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Capacity added1,410 MW
Annual energy3,840 GWh
Commissioned2018
01 · The situation

What happened

The World Bank’s February 2020 factsheet reports that a 1,410 MW power plant had been installed on the fourth tunnel at Tarbela. It describes the aim of supplying relatively low-cost power during high-demand summer months. The fifth extension is a separate project for a different tunnel. Credit for that additional capacity does not belong in an appraisal of the fourth extension.

A reservoir serving irrigation releases water for reasons beyond electricity prices. Running an existing release through a turbine can create energy value without a proportional increase in withdrawals. The actual gain depends on head, timing, station availability and whether the grid can use the output. A summer MWh that displaces expensive alternative generation can be worth more than an identical MWh when surplus power is available.

Tarbela Dam on the Indus, completed in the mid-1970s, was built with five tunnels. Tunnels 1 to 3 carried power plants with 3,478 MW of capacity, while tunnels 4 and 5 were used mainly to release water for irrigation. The Tarbela Fourth Extension added a power station on tunnel 4, so water already released for farms could also generate electricity.

The project installed three 470 MW units, adding 1,410 MW and raising Tarbela’s capacity to 4,888 MW. The World Bank provided about US$840 million and WAPDA US$74 million. Construction began in October 2013 and the plant was commissioned in phases in 2018. In 2020 the World Bank said the project had started generating on time, at a cost about 10 percent below the budget, and that its benefits were about twice its capital cost.

Because no new dam was needed, the main costs were the powerhouse, intake modifications and transmission. Intakes for tunnels 3 and 4 were raised to protect against sedimentation in the reservoir. By late 2020 the extension had generated over 12,000 GWh. A fifth extension on tunnel 5, adding 1,530 MW, followed with further World Bank financing.

02 · Timeline

Key moments

  1. Tarbela Dam completed

  2. T4 construction starts

  3. T4 commissioned in phases

  4. World Bank reports cost about 10 percent below budget

03 · Exhibit
Exhibit 1 · Tarbela power station capacity
MW3,478Before T4 (tunnels 1–3)1,410Added by T44,888After T41,530Planned T5 addition

T4 was financed with about US$840 million from the World Bank and US$74 million from WAPDA. Sources: Dawn; ProPakistani; World Bank.

04 · Core tensions

The trade-offs at the heart of the case

Core tensions

Comparing the extension with a new standalone dam would answer only one possible investment question. Another option is to keep the existing releases and purchase replacement electricity in the relevant hours. The latter comparison captures fuel prices, demand timing and constraints on transmission. A project can pass an annual-average comparison and perform poorly in the hours that drive system costs.

The irrigation manager’s timetable

An electricity planner may see a few peak-price hours and ask the reservoir operator to shift releases into them. A farmer waiting at the tail of a canal may experience the same shift as a missed irrigation turn. Changes of timing can have consequences metres downstream and days later that never appear on the generating station’s output meter. An appraisal should assign any operational flexibility only after consulting the people who manage those constraints. There is also an investment boundary around the existing dam. Cost savings from reusing civil works are genuine, but common infrastructure still needs inspection and maintenance. A generating addition can increase demands on shared facilities or require outages affecting other units. Estimate incremental costs against an operating dam without the extension. Allocating all historical dam costs to the new turbines would penalise the investment, while assigning none of the new shared costs would exaggerate its return. Engineering and accounting teams need to agree which work would have occurred anyway.

The power a release would have produced anyway

When water must be released for another purpose, its passage through an additional turbine can generate electricity without a separate increase in water released. That observation is the starting point for valuing a tunnel conversion, not the full calculation. A planner must ask where that same water would otherwise have gone. If an existing unit could already have used it, crediting every new meter reading as incremental generation exaggerates the value of the extension. If it would have bypassed productive capacity, the incremental value can be substantial. Construct a comparison for the hours when water availability, operating rules and demand are similar. Identify the marginal power source that would run without the extension, its fuel cost and whether it can turn down when hydro output arrives. A generation reading in a low-value period is financially different from the same reading when a costly alternative is operating. This also sharpens the maintenance decision. A planned outage coordinated with low-value releases can protect much of the annual economic benefit even when the unit’s reported availability falls.

Irrigation sets the timetable

Water at Tarbela is released mainly to meet irrigation needs set by provincial water accords. Power planners might prefer to release water during peak electricity hours, but farmers need water when crops need it. The extension generates most in summer, when irrigation releases are high and power demand peaks, which aligns the two.

Cheap power, shared costs

Electricity from an existing dam is very cheap at the margin because the dam was built long ago. That makes extensions attractive, but it can also hide the need to maintain the original structure and manage sediment, which threatens long-term storage.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    Which water releases provide the cleanest comparison for incremental generation?

  2. Q2

    How would the answer change if demand peaked later than the irrigation release?

  3. Q3

    How would you value an extra megawatt-hour when an alternative generator cannot reduce its output?

Frameworks worth applying
  • Brownfield investment
  • Using existing assets
  • Seasonal power value
  • Cost control
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

Adding turbines to an existing tunnel was one of the cheapest ways to expand Pakistan’s clean power supply. The lesson is to look first at under-used existing assets before building new ones.

  1. Use existing infrastructure

    Add capacity where structures already exist.

  2. Align with irrigation

    Schedule generation around water releases.

  3. Manage sediment

    Invest in reservoir life alongside turbines.

What this plan gives up

Brownfield extensions are cheap but depend on old infrastructure.

The strongest counter-argument

Relying on Tarbela concentrates generation at one site and depends on a reservoir that is gradually filling with sediment.

Metrics to watch

  • Annual generation from T4
  • Reservoir sedimentation rate
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.