Karot Power Company

Who takes the dry-year risk at Karot?

A dam’s turbines carry a nameplate rating. A lender receives cash from electricity delivered and paid for under a contract. Between the two lie river flows, plant availability, grid access and the ability of a purchaser to pay on time.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Capacity720 MW
Debt to equity80:20
Commercial operation29 June 2022
01 · The situation

What happened

Pakistan’s Private Power and Infrastructure Board lists Karot on the Jhelum, at the boundary of Rawalpindi and Kotli districts. It records 720 MW gross capacity and 712.8 MW net capacity, with four 180 MW units. The project price was about US$1.70 billion and the reported financing split was 80% debt and 20% equity. The board lists commissioning on 29 June 2022.

Gross output includes power used by the station itself. Net capacity is a better starting point when estimating deliveries, but still gives only an instantaneous maximum. Debt payments can fall due in a dry quarter even if annual generation subsequently recovers.

Karot is a 720 MW run-of-river hydropower plant on the Jhelum River, about 55 km from Islamabad. It was the first hydropower project under the China–Pakistan Economic Corridor and the first investment of China’s Silk Road Fund. China Three Gorges Corporation developed it through Karot Power Company under a 35-year build-own-operate-transfer concession. Four 180 MW turbines are expected to produce about 3.2–3.4 billion kWh a year.

The Private Power and Infrastructure Board lists a total project price of about US$1.70 billion, financed 80 percent with debt and 20 percent with equity. China Development Bank, China Eximbank and the Silk Road Fund provided a US$1.29 billion syndicated loan. Construction began in December 2016; Covid-19 led to an extension of the required commercial operation date, but the plant began full commercial operation on 29 June 2022, ahead of the revised deadline.

Under Pakistan’s power policy, such plants are paid largely through capacity payments, which cover debt and equity returns as long as the plant is available, plus energy payments for electricity actually delivered. That structure shifts much of the hydrology risk away from the investor to the power purchaser and ultimately to consumers.

02 · Timeline

Key moments

  1. Construction begins

  2. Diversion gates closed; reservoir starts filling

  3. First unit ready to generate

  4. Full commercial operation

03 · Exhibit
Exhibit 1 · Karot hydropower project
as stated720Capacity (MW)3,436Expected annual output (GWh)1,698Total project price (US$ m)1,292Syndicated loan (US$ m)

Financed 80:20 debt to equity; 35-year build-own-operate-transfer concession. Sources: PPIB; AidData; Wikipedia.

04 · Core tensions

The trade-offs at the heart of the case

Core tensions

More borrowing can improve the sponsor’s equity return in a good year. It can also reduce operating freedom when hydrology is poor or invoices go unpaid. A cash reserve is expensive in normal months but buys time to avoid a distressed refinancing. Equity sponsors and lenders therefore have different incentives when discussing how much to retain after a wet season.

A wet year can be a poor year for collections

Heavy water flows can support strong generation at several plants at once. Depending on the grid and contract terms, abundant generation can also coincide with constraints on dispatch or periods when a purchaser delays settlement. The operator’s finance team needs to know whether a reported shortfall comes from water, station performance, grid instructions or receipts outstanding. Treating each as poor plant operation would direct spending toward the wrong problem. The lender’s interest becomes especially clear near a debt-service date. Two operating years with identical annual cash collections can produce different payment outcomes if one year’s large receipt arrives after the instalment is due. A reserve placed under enforceable control can address that timing exposure. Its design also affects the shareholders, who may be unable to distribute otherwise available cash. Set out the release conditions and replenishment rule and model the next period after any draw. A reserve used twice without replenishment offers only one season of protection.

Who bears a dry year

In a dry year, a run-of-river plant produces less electricity. If capacity payments continue regardless, the buyer pays for power it did not receive. That protects lenders, who need predictable cash to accept 80 percent leverage, but raises the cost of electricity in years when it is scarce.

Paying on time

A plant can be fully available and still face cash problems if the state power purchaser pays late. Pakistan’s circular debt, the build-up of unpaid bills in the power sector, has repeatedly delayed payments to independent power producers, putting pressure on their ability to service debt.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    How much output is absorbed between gross and net capacity at rated operation?

  2. Q2

    Which party can best manage each cause of a shortfall in cash receipts?

  3. Q3

    Which records would distinguish a dry-year generation shortfall from a late payment for delivered power?

Frameworks worth applying
  • Project finance
  • Hydrology risk
  • Capacity payments
  • Leverage
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

Karot shows how high leverage and capacity payments make large hydropower investable, but also how much risk they transfer to consumers. Pakistan’s ability to pay on time is as important to such projects as rainfall.

  1. Match debt to cash flow

    Size borrowing to cover dry-year revenues.

  2. Pay producers on time

    Reduce circular debt to protect project finance.

  3. Report availability and output

    Publish both to show what consumers pay for.

What this plan gives up

Capacity payments attract investment but make consumers pay for unused capacity.

The strongest counter-argument

Without capacity payments, few investors would finance hydropower in Pakistan, and the country would rely more on imported fuel.

Metrics to watch

  • Annual generation versus expected
  • Payment delays from the power purchaser
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.