Case study · SingaporeEnergy security2010–2013Last reviewed 22 November 2026

Singapore case studiesAsia-Pacific case studiesEngineering case studies

Singapore LNG Corporation

A second way to get gas into Singapore

A pipeline connects a buyer to a particular geography. A liquefied natural gas terminal connects it to ships, suppliers and shipping schedules. Singapore opened its first commercial LNG import terminal in 2013 to add that second route to an economy heavily reliant on imported gas.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Commercial launch7 May 2013
Initial capacity3.5m tonnes/year
Initial storage2 tanks
Initial marine access1 jetty
01 · The situation

What happened

The initial facility had a jetty, two storage tanks and the ability to regasify about three and a half million tonnes annually. Regasification converts the shipped liquid back into gas for the domestic network. A tank does not produce fuel. It creates time between an arriving ship and demand from customers ashore, provided inventory is available when needed.

Singapore received a commissioning cargo in March 2013 and its first commercial cargo in May. A commissioning shipment tests the facilities and operating arrangements; the later cargo marked the commercial milestone. Treating the two as identical would overstate the period over which customers could rely on routine service. The initial two tanks also created a useful separation between stored energy and flow capacity, two quantities measured in different units.

Security of supply and commercial throughput can point in opposite directions. Empty space in a tank may look inefficient to a terminal seeking higher utilisation. It can be valuable to a system operator expecting an unscheduled cargo or a pipeline disruption. Singapore also remains exposed to global prices, competition for ships and the terms of long-term contracts. A new import route removes one concentration while introducing different dependencies.

A buyer can hold many days of gas equivalent in a tank and still be unable to deliver enough gas in the busiest hour if regasification capacity is tight. Conversely, a large regasification plant cannot send out fuel that the tanks do not hold. Model inventories as a stock replenished by vessel arrivals and output as a rate constrained by equipment. That distinction is particularly important when multiple users count the same spare terminal capacity in their contingency plans.

Singapore depends on natural gas for most of its electricity; in 2013 more than 90% of power was generated from gas, most of it piped from Malaysia and Indonesia. To diversify supply, the government decided in 2006 to build a liquefied natural gas terminal on Jurong Island. The Energy Market Authority set up Singapore LNG Corporation in 2009, construction began in 2010, and the S$1.7 billion terminal started commercial operations on 7 May 2013.

The terminal opened with two storage tanks, one jetty and capacity of 3.5 million tonnes a year. A third tank and second jetty raised capacity to 6 million tonnes in 2014. A fourth tank of 260,000 cubic metres, among the largest in the world, brought capacity to about 11 million tonnes by 2018, enough, the chief executive said, to meet Singapore’s needs even if piped imports stopped.

Building capacity well ahead of normal demand is costly, and in 2018 the terminal was using only about 2.5 million tonnes of its regasification capacity, though its storage was nearly full. The value lies in resilience. When pipeline supplies are interrupted, or when global LNG becomes cheaper than piped gas, the terminal gives Singapore a choice. The government has since studied a second terminal using a floating storage and regasification unit with up to 5 million tonnes a year of capacity.

The terminal also supports Singapore’s ambition to be an LNG trading hub. Spare storage and jetties allow traders to store cargoes and reload them onto smaller ships, and the terminal can supply LNG as fuel for ships, which is growing as shipping looks for cleaner alternatives to heavy fuel oil.

02 · Timeline

Key moments

  1. Construction of the import terminal began.

  2. The first commercial LNG cargo arrived in May.

  3. Additional tanks and regasification capacity were planned.

03 · Exhibit
Exhibit 1 · Singapore LNG terminal throughput capacity
Million tonnes per year3.52013 opening (2 tanks)6.02014 (3 tanks)11.02018 (4 tanks)

The fourth tank, 260,000 m³, was among the world’s largest. The initial terminal cost S$1.7bn. Sources: SLNG; EMA; Maritime Executive.

04 · Core tensions

The trade-offs at the heart of the case

A cargo in the wrong week

Imagine a buyer secures an attractive price for a replacement cargo but the ship arrives after the tanks are nearly empty. The value of the contract turns on inventory days, vessel access and regasification space. A supplier agreement that cannot meet the critical window is less effective insurance than its annual tonnage suggests. Record the time from recognising a shortage to usable gas entering the network. Diversification should be assessed across supply failures that could happen together. Two contracted LNG sellers may load from the same constrained region or depend on a common shipping route. A pipeline and a terminal may still share domestic equipment needed to deliver gas to customers. Counting supplier names or import channels therefore overstates resilience if the common bottleneck is ignored. A more useful map links each promised volume to a physical route, arrival window and alternative use during stress. The cheapest insurance may be removing one common bottleneck rather than signing another nominally independent contract.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    When is empty tank space an asset for the grid?

  2. Q2

    What costs remain exposed to world prices after import routes diversify?

  3. Q3

    Which constraint binds first in an extended supply interruption?

  4. Q4

    How would you test whether exceptionally mild demand during a trial interruption explains the evidence?

  5. Q5

    Which observation would most change your estimate of the time purchased by storage, and why?

Frameworks worth applying
  • Energy security
  • Building ahead of demand
  • Regulated returns
  • Supply diversification
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

Compare the terminal with a credible portfolio of pipeline supply, demand response and alternative cargo contracts. Account for how long it takes to secure and unload a replacement shipment. Assign a cost to reserving capacity for emergencies so public resilience requirements do not quietly displace profitable commercial services.

  1. Diversify supply

    Add a second route for gas so the country is not dependent on pipelines from neighbours.

  2. Expand in phases

    Start with two tanks and add capacity as contracts and demand become clear.

  3. Use spare capacity commercially

    Offer storage and reloading to traders to earn income from capacity built for security.

What this plan gives up

An import terminal gives Singapore security against pipeline disruptions, but much of its capacity sits unused in normal times, so its value is partly insurance that is hard to price.

The strongest counter-argument

A decision based entirely on rare disruptions could justify far more spare capacity than customers can afford. Show how the first tank, the next tank and the last increment of regasification capacity change the duration and severity of a shortage. Their incremental contributions can differ substantially.

Metrics to watch

  • unserved demand after available inventory and alternative supply
  • the time purchased by storage
  • LNG share of gas imports
  • Terminal utilisation
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.