What happened
A ferry operator can see the outline of a ship long before the vessel can carry an island resident home. The two Clyde and Hebrides vessels made that distinction painfully practical. By March 2022 Audit Scotland put estimated cost at at least £240 million, about two and a half times the original vessels budget. The sponsor still needed vessels and island communities still needed dependable sailings. The decision was whether another payment would buy verifiable progress towards an operable service.
A shipyard can use cash to sustain skills and supplier relationships while documenting little progress on the component holding up commissioning. Equally, withholding a payment can interrupt precisely the work needed to complete a vessel. The state had an interest in the industrial workforce as well as in the ships. Combining those objectives in an undifferentiated payment makes it impossible to tell whether management bought additional capability or simply postponed running out of cash.
Compare an inspected compartment with one that looks complete but awaits design approval. Installed equipment may have to be removed if the interfaces are wrong. An earned-value schedule should identify the rework outstanding, which supplier owns the design and what test counts as acceptance. The share of steel already fabricated answers a narrower question.
Audit Scotland reported that the preferred bidder could not provide the full refund guarantee included among the contract requirements. That detail changes the significance of a progress payment. A refund guarantee is valuable when the party accepting an advance cannot finish the work. If the protection is weaker, the sponsor should examine both the expected cost of failure and the cash needed to secure unfinished work before a replacement can take control.
For each outstanding system, identify the person or supplier capable of validating it and how long it would take to replace them. A payment that retains a scarce specialist can be justified if it changes the shortest feasible route to commissioning. The same payment has less value if the necessary design is still unresolved. Link the retention payment to access, documentation and succession so that the sponsor does not have to pay repeatedly for the same dependency. Separately, ask the island operator when a completed vessel could enter the timetable. Harbour compatibility, training and the relief fleet can move the date at which a shipyard milestone turns into a usable public service.
In 2015 the Scottish Government’s ferry-asset company CMAL ordered two dual-fuel ferries for CalMac, the Glen Sannox and the vessel later named Glen Rosa, from Ferguson Marine in Port Glasgow. Ferguson, the only Scottish bidder, offered to build both for £97 million, with delivery due in 2018. The ships were designed to run on liquefied natural gas or marine gas oil.
The project went badly wrong. Designs were reworked repeatedly, disputes broke out between the yard and CMAL, and in 2019 the Scottish Government took the yard into public ownership after it entered administration. At one hearing the yard’s chief executive said about £35 million of recent cost increases on Glen Sannox came directly from re-working the design. By 2024 the combined cost was put at close to £400 million, including a £45 million loan that was written off.
Glen Sannox was finally delivered in November 2024 and entered service to Arran in January 2025, more than six and a half years late. In 2025 the yard raised the estimate for Glen Rosa again, taking the cost of both ships to more than £460 million, over four times the original price, and pushed delivery to at least April 2026. The ships also cannot use Ardrossan harbour until 2029, so they operate from Troon.
Key moments
Ferguson Marine is announced as preferred bidder.
Both original delivery dates pass.
Audit Scotland reports unresolved operational problems.
Later figures include costs after the yard was nationalised and written-off loans; estimates are rounded as reported. Sources: Audit Scotland via GPT package; Wikipedia; The Scotsman; STV; Holyrood.
The trade-offs at the heart of the case
A comparison with Metronet: The supply chain after the contractor is in difficulty
The Metronet report asked why a shareholder-dominated supply chain had escaped effective challenge even though private companies formally carried delivery responsibilities. A Scottish ferry sponsor confronts a related problem when the only team able to complete a difficult system sits inside a financially distressed yard. The contract gives the public buyer rights; the operating environment determines what using those rights will cost.
What to watch
For a lifeline route, the economics of delay reach beyond the contract price. An ageing spare vessel may need extra maintenance and a disruption can leave perishable goods awaiting a later sailing. Establish which of those losses are borne by the operator and which by households and businesses. Count replacement capacity where it genuinely reduces losses. Keeping a ferry nominally available is of little value if its capacity or harbour compatibility prevents it from working the affected route.
For your seminar, paper or interview
- Q1
Which milestone is hardest to certify independently?
- Q2
What would justify a separate budget to preserve shipbuilding capability?
- Fixed-price contracts
- Milestone payments
- Sunk cost fallacy
- Industrial policy
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
Fund a short, independently costed completion sequence with explicit acceptance evidence for each milestone. Authorise any wider shipyard support through a separate decision and explain the expected employment and industrial benefits on their own terms.
Award to the local yard
Choose Ferguson Marine, the only Scottish bidder, despite weak guarantees.
Nationalise the yard
Take Ferguson into public ownership in 2019 to finish the ships.
Keep building
Complete both ferries rather than restart elsewhere.
What this plan gives up
Finishing the ships protected jobs and avoided writing off work already done, but it kept public money flowing into a yard that repeatedly missed costs and dates.
The strongest counter-argument
An aggressive payment hold can put specialist subcontractors at risk. Prioritising payments directly linked to scarce skills or equipment may preserve options. The sponsor still needs visibility of exactly what has been secured and which claims remain against it.
Metrics to watch
- Glen Rosa delivery date
- Ferry reliability on Arran routes
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- Audit Scotland: New vessels for the Clyde and Hebrides ↗
- Audit Scotland: March 2022 findings ↗
- National Audit Office: The failure of Metronet ↗
- Gov.scot: Costs and dates for MV Glen Sannox and MV Glen Rosa (FOI) ↗
- The Scotsman: Further delays as potential cost hits almost £400m ↗
- STV: CalMac ferry delayed another six months as costs soar ↗
- STV: £35m spent solely on redesigns ↗
- Maritime Executive: More delays and cost overruns for Glen Rosa ↗
- Image: AI-generated editorial illustration
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.