What happened
A government can set an upper price for renewable electricity. It cannot order a private developer to submit a financeable bid at that price. The UK’s fifth allocation round drew no offshore wind bids. By the next round new fixed-bottom offshore capacity secured contracts at £58.87 per megawatt-hour in 2012 prices. For procurement officials, the empty round mattered because time without an award can consume planning and supply-chain capacity even when no subsidy is committed.
The £44 figure for the fifth round was a ceiling. The £58.87 figure for new fixed-bottom offshore wind in the sixth was an award price. Their difference is £14.87 on a common price basis, but these numbers are not two observed market-clearing prices. With no bids in the first round, the lowest price that would have attracted enough credible capacity was unobserved.
A developer deciding whether to enter weighs turbine prices, financing, grid access, construction dates and the value of keeping the project available for a later auction. Refusing to bid can be rational even if a project appears capable of covering its expected costs. A tight construction schedule and uncertainty over future contract prices give waiting an option value.
The inflation base also matters when comparing auction headlines over time. A figure expressed in prices of 2012 is not the sterling cash settlement for a later delivery year. Use a common real price basis to compare contract terms. Use indexed nominal prices when modelling the cash the project and its lenders expect to receive. Mixing a real revenue stream with inflated future procurement costs would make a project look artificially unattractive.
A developer can decline to bid because its costs are high, because grid access is uncertain, because a supplier will not fix a price, or because it expects better terms in the next round. All can produce the same observable outcome. Interviewing nonparticipants helps, but bidders have a reason to emphasise tight economics when government is about to set a ceiling. Compare their accounts with dated financing terms, equipment quotes and the requirements of alternative markets. Then look at what changed when bids returned. A successful subsequent round shows that the later package attracted participation. It cannot identify a single cause for the earlier absence of bids without additional evidence.
Britain supports new renewable power through contracts for difference, awarded in auctions. Developers bid the strike price they need; consumers pay the difference when market prices are lower and receive it back when they are higher. In the fourth round, AR4, announced in July 2022, five large offshore wind projects totalling about 7 GW cleared at a record low of £37.35/MWh in 2012 prices, for delivery in 2026/27.
Then costs rose sharply as inflation and interest rates climbed and turbine and installation prices jumped. For AR5 in 2023 the government set the maximum offshore price at £44/MWh, only slightly above AR4, and no offshore wind developer bid. For AR6 it raised the cap by 66% to £73/MWh; projects cleared at £58.87 and £54.23. Several AR4 winners used a rule to move part of their capacity into AR6 at the higher price, and Ørsted later cancelled Hornsea 4, an AR6 winner.
In January 2026 the AR7 results awarded about 8.4 GW of offshore wind, the largest ever, at about £65.45/MWh in 2012 prices, or about £91/MWh in 2024 prices. The sequence shows that in an auction, a reserve price below true costs does not lower prices; it simply produces no supply.
For developers, the auction price must cover turbines, foundations, cables, vessels and financing over decades. When interest rates rise, the financing cost alone can add substantially to the price needed, which is why offshore wind, a capital-intensive technology, was hit harder than many other sources of power.
Key moments
Earlier awards provide a low-price benchmark.
AR5 attracts no offshore wind bids.
AR6 publishes new fixed-bottom offshore awards.
AR7 offshore projects cleared at about £91/MWh in 2024 prices. Some AR6 capacity cleared at £54.23. Sources: S&P Global; Energy Institute; IJGlobal; GOV.UK AR7 results.
The trade-offs at the heart of the case
A comparison with Hinkley Point C: What Hinkley adds to an auction designer’s questions
The Hinkley Point C case makes an important characteristic of procurement visible. A revenue contract can reduce investors’ uncertainty and thereby change what they are prepared to build. Its value is determined by the price basis, duration, available output and date at which supported payments begin. An apparently low offshore ceiling can therefore be less attractive than it looks if other terms leave a developer exposed to an expensive delay.
What to watch
A no-bid outcome is informative but incomplete. It tells a buyer that the offered terms did not attract participation on the day. It cannot identify how much extra revenue each project required or whether non-price conditions were decisive. Contacting unsuccessful or absent bidders and checking their claims against supplier quotations and finance terms improves the next auction design. Treat those responses as evidence from interested parties and test them against actual offers when the market reopens.
For your seminar, paper or interview
- Q1
Would you raise the ceiling, adjust delivery dates or change both?
- Q2
Which measurement would distinguish awarded capacity from capacity likely to reach operation?
- Reverse auctions
- Reserve prices
- Winner’s curse
- Supply-chain inflation
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
Set auction ceilings using updated deliverable project economics. Compare the cost of a more generous ceiling with the cost of a round that buys no offshore generation. Publish contracted capacity and follow the projects through financing, construction and actual output.
Set a low price cap
Cap AR5 offshore bids at £44/MWh.
Raise the cap after failure
Lift the AR6 cap to £73/MWh.
Expand the budget
Award a record 8.4 GW in AR7 at higher prices.
What this plan gives up
Tight price caps protected bill-payers in the short term, but when they were below developers’ costs they produced no projects, delaying clean power and adding the cost of waiting.
The strongest counter-argument
Metrics to watch
- AR8 clearing prices
- Projects that cancel after winning
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- Department for Energy Security and Net Zero: allocation round 6 results ↗
- World Bank: UK offshore wind auction case study ↗
- National Audit Office: Hinkley Point C ↗
- S&P Global: UK awards 10.8 GW at record low strike prices (2022) ↗
- Energy Institute: UK secures 8.4 GW of offshore wind ↗
- IJGlobal: Offshore wind, striking the right note ↗
- GOV.UK: Contracts for Difference Allocation Round 7 results ↗
- Oxford Smith School: Do AR7 results mark the end of growing pains? ↗
- Image: AI-generated editorial illustration
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.