Skip to the lesson
Back to the library
Lesson 420Behavioural finance4 min readLast reviewed 21 November 2026

More behavioural finance lessonsAll lessons

IT ALWAYS TAKES LONGER

The planning fallacy: why projects cost more and take longer.

Why people underestimate the time, cost and risk of their plans, from home renovations to business launches, and how outside views and buffers lead to better budgets.

See the example
The planning fallacy: why projects cost more and take longer. — photo illustration
420 / IT ALWAYS TAKES LONGERPhoto illustration
01

The idea

The planning fallacy is our tendency to underestimate how long tasks will take and how much they will cost, even when we know similar tasks have run late before. Psychologists Daniel Kahneman and Amos Tversky described it in 1979.

It affects everyone from students and homeowners to governments and large companies. In personal finance, it shows up in budgets for weddings, renovations, moving countries, starting a business and saving goals.

At a glance
The planning fallacy: why projects cost more and take longer.
02

The evidence

In a well-known 1994 study, psychologists Roger Buehler, Dale Griffin and Michael Ross asked students to predict when they would finish their honours thesis. The average prediction was about 34 days; the average actual time was about 56 days. Even when asked for a 'worst-case' estimate, many students still finished later.

Large projects show the same pattern. Sydney Opera House was planned to open in 1963 at a cost of about A$7 million. It opened in 1973 at a cost of about A$102 million. Studies of infrastructure projects by Oxford professor Bent Flyvbjerg have found that the large majority run over budget, many by a wide margin.

03

Why it happens

When planning, we focus on our specific project and imagine how it will go if things go roughly to plan. We picture the steps, not the interruptions, delays, mistakes and surprises that usually happen. We also tend to treat each project as unique, ignoring what happened last time.

Optimism and motivation play a part. We want the project to be quick and affordable, and that hope shapes our estimate. In business and government, there can also be incentives to present low estimates to get approval.

04

Where it hits your money

The planning fallacy shows up in many everyday financial plans.

PlanCommon underestimateTypical overrun
Home renovationCost and timeOften 20–50% over budget
Wedding or big eventExtras and guest numbersMany final bills exceed plans
Moving abroadSet-up costsDeposits, fees, furniture, visas
Starting a businessTime to profitCash runs out early
Saving goalHow long it will takeLife events interrupt saving
05

Take the outside view

Kahneman recommended taking the outside view: instead of starting from your own plan, start from how similar projects turned out for others. How long do kitchen renovations in your area usually take? What did friends' weddings really cost? How long did comparable businesses take to break even?

This approach, known as reference class forecasting, is now used by some governments for large projects. It works for households too.

06

Build in buffers

Once you have an estimate, add a buffer. A common rule for renovations is to add 15% to 25% to the budget and extra time to the schedule. For a new business, plan for income to take longer to arrive than you hope and keep enough cash to survive at least six to twelve months without profits.

Breaking big projects into stages, with a review after each, helps you spot overruns early and adjust before costs spiral.

07

Plans and savings goals

The planning fallacy affects saving too. People often assume they will save a fixed amount every month for years. In reality, holidays, repairs, family needs and job changes interrupt plans. Setting slightly more conservative targets, automating savings and reviewing progress regularly make goals more achievable.

08

The planning fallacy at work

Many people underestimate how long it will take to earn a promotion, finish a qualification or build a business to the point where it pays a salary. Career plans that assume steady progress can leave little room for setbacks, which can affect savings and borrowing decisions. Planning for slower progress, and treating faster success as a bonus, makes financial plans sturdier.

09

Why we never learn

People often remember past projects as having gone more smoothly than they did, which helps the planning fallacy repeat. Keeping a simple record of planned versus actual costs and times for your own projects, such as moves, renovations or events, gives you personal data for next time. Your own history is one of the best reference classes you have.

10

Using pre-mortems

A useful technique from psychologist Gary Klein is the pre-mortem. Before starting a project, imagine it has gone badly over budget and late, then list all the reasons why. This makes it easier to spot risks that optimism hides, such as permit delays, supplier problems or illness, and to plan for them before they happen. Even ten minutes of this exercise often changes a budget.

11

A realistic scenario

Kenji and Aiko in Osaka plan a ¥3 million kitchen renovation over six weeks. Before signing, they ask three friends who renovated recently; all went over budget, by 20% to 40%, and took longer. They set a budget of ¥3.75 million, plan for ten weeks, and keep their emergency fund separate. When hidden plumbing problems appear, the project costs ¥3.6 million and takes nine weeks, within their adjusted plan.

12

Questions to ask before you start

Ask yourself
  • How long and how much did similar projects take for others?
  • What could go wrong that I haven't included?
  • Have I added a buffer for time and money?
  • Can I break this into stages with reviews?
  • Will my emergency fund stay untouched if it overruns?
13

The short version

The planning fallacy makes us underestimate time and costs because we picture our plan going smoothly. Use the outside view, add generous buffers, break projects into stages, and protect your emergency fund from overruns.

Worked example

Illustration: in a classic study, students estimated their final thesis would take about 34 days on average. It actually took about 56 days. Fewer than a third finished by their own predicted date.

The idea to take with you

Your plan is probably too optimistic. Look at how similar projects actually turned out, and add generous buffers for time and money.

Sources & assumptions

Primary educational reference

Buehler, Griffin & Ross · Exploring the planning fallacy (Journal of Personality and Social Psychology, 1994) ↗

Reviewed November 21, 2026. Examples are hypothetical illustrations in AED or USD. Educational content, not personalised investment, legal or tax advice.