What happened
ASX announced a reassessment of its CHESS replacement project after an independent review and an internal assessment. It expected to derecognise A$245 million to A$255 million of capitalised software before tax. The estimated after-tax range was A$172 million to A$179 million. Recording the charge changed the book value attributed to past development. It did not answer whether to repair, replace or redesign the system while keeping existing settlement services reliable.
Capitalisation spreads qualifying development expenditure over expected future use. When the evidence supporting those benefits changes, a write-down can expose years of earlier spending in a single reporting period. Investors still need to know how much future engineering, industry testing and operational support each feasible option requires. A lower historical carrying value does nothing to reduce the work that remains before participants can safely migrate.
CHESS is the ASX system that clears and settles share trades and records ownership. In 2016–2017 ASX began a project to replace it with a system built by Digital Asset using distributed ledger technology. The project was repeatedly delayed, and in 2022 go-live was pushed back again to 2024.
In August 2022 ASX commissioned Accenture to review the project. Its report found significant challenges with the solution design and its ability to meet ASX’s requirements, including higher latency, complexity and an uncertain timeline. It also suggested reconsidering whether distributed ledger technology was the right choice.
On 17 November 2022 ASX paused all current activities and said it would derecognise capitalised software, a non-cash charge of A$245–255 million before tax, or A$172–179 million after tax, in the first half of FY2023, with no impact on dividends. It appointed a new project director. Regulators ASIC and the Reserve Bank said they expected ASX to bear the costs, noting the industry had incurred significant expense.
Capitalising software costs spreads them over future years; when a project fails, the remaining value must be written off at once. The case shows why boards should monitor large technology projects closely.
Key moments
ASX announces independent review
ASX reassesses and estimates derecognition
Independent assurance assessment published
Non-cash derecognition of capitalised software in the first half of FY2023; no impact on dividends. Source: ASX (November 2022).
The trade-offs at the heart of the case
What makes a rehearsal persuasive?
A demonstration can show that one trade settles under ideal conditions. A market operator has to know what happens to all participants if something fails partway through the day. That requires a rehearsal covering the starting positions, subsequent obligations and a verifiable end state. Independent participants must be able to match their records without relying on the project team’s explanation. The financial value of such a rehearsal is the opportunity to discover contract and design issues while changing course is still possible. It also produces evidence that can be compared with the next funding request. A participant firm must decide when to commit its own people to an industry migration. If dates repeatedly move, it can incur implementation costs without receiving any of the new system’s benefits. The operator’s expenditure is therefore only part of the economic total. Ask participants for estimated costs of parallel running, training and interface changes under each option. An apparently cheap design that pushes conversion work onto dozens of users may be more expensive for the market as a whole.
Testing the evidence
An analyst could ask whether the apparent effect survives a fair comparison. Start with settlement scenarios exercised end to end, then identify scenarios demonstrated only within a single component. Follow reconciled settlement completion under agreed conditions for both groups across matching periods. A single difference at the end says little if the two groups were already diverging beforehand. Plot the earlier histories and investigate differences in participant readiness and test complexity before attributing the subsequent gap to the decision. Independent corroboration would come from independently reconciled results from representative settlement rehearsals. Match the dates as carefully as the amounts. A forecast that ultimately comes true can still leave the decision maker short of funding in the intervening period, particularly when another party controls an important milestone.
For your seminar, paper or interview
- Q1
What evidence would justify another tranche of development spending after the carrying value has been written down?
- Q2
How would you use scenarios demonstrated only within a single component to test changes in reconciled settlement completion under agreed conditions, while allowing for differences in participant readiness and test complexity?
- Q3
Compare the recommended course with a modular replacement with independently accepted components and a supported incumbent service. Which commitment would you make first, and what result would cause you to change course?
- Capitalised software
- Project governance
- Technology risk
- Market infrastructure
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
Require an independently witnessed settlement rehearsal with participant firms before releasing the next major funding tranche. Document exception handling, reconciliation and fallback arrangements in terms participants can verify. Separate the budget for maintaining the existing service from the budget for replacing it, so project delays cannot silently cannibalise operational resilience.
Get an independent review
Commission an outside assessment when deadlines slip repeatedly.
Pause and redesign
Stop current work and revisit the solution design rather than push on.
Keep the old system stable
Maintain the existing CHESS while the replacement is reconsidered.
What this plan gives up
Pausing the project and writing off the investment cut losses and restored credibility with regulators, but it left the market on a 25-year-old system for longer and wasted years of industry effort.
The strongest counter-argument
A modular replacement can narrow the scope of one change and let participants validate components progressively. It also creates interfaces that must work reliably while old and new elements coexist. Compare the cost of that transitional complexity with the risk of a single coordinated change. Both alternatives require a funded plan for keeping the incumbent service dependable. Consider whether supplier contracts reward completion of a technical milestone or usable service demonstrated by market participants. If a vendor earns payment for delivering code while the exchange bears integration risk, both can report progress in good faith while their economic positions diverge. Align milestones with evidence that can be reproduced independently. Retain a funded route to recover or replace work if the next test shows the design cannot meet an essential market requirement. Define failure conditions before approving the test. A rehearsal with no possible outcome that triggers reconsideration is unlikely to improve the investment decision.
Metrics to watch
- New CHESS replacement timeline
- Regulatory actions against ASX
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- ASX · Reassessment and derecognition, November 2022 ↗
- Independent assessment · CHESS replacement assurance programme ↗
- ASX: Reassessment of CHESS replacement and derecognition (2022) ↗
- The Register: ASX pauses blockchain project ↗
- Reuters (via Yahoo): ASX flags hit from clearing software halt ↗
- Image: AI-generated editorial illustration for Simplifying Finance. Illustrative scene.
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.