bp and Tangguh partners

How much of an LNG expansion is already sold?

A liquefaction train turns a gas supply into a product that ships can deliver. The term train refers to a processing line. Its economic value depends on a set of other assets being ready together, including producing fields, storage, loading facilities and transport. Paying for the train while one of the other links is unavailable produces a capacity figure with little corresponding cash.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Total capacity11.4 mtpa
Train 3 delayAbout four years
Cargoes to Indonesia, 202585
01 · The situation

What happened

The Tangguh partners announced the expansion investment decision in July 2016. They specified a third train capable of 3.8 million tonnes a year in addition to 7.6 million tonnes of existing capacity . In October 2023 bp reported that the first Train 3 cargo had sailed for PLN, its domestic foundation customer, and put total capacity at 11.4 million tonnes a year . The first shipment was a milestone. It was not evidence of a full year at rated output.

The investment decision named two existing trains and a third to be added . That shared footprint changes the appraisal. Existing storage or marine infrastructure can lower expansion costs, but a disruption affecting a shared facility can interrupt more than one train’s deliveries.

bp operates Tangguh with a 40.22 percent interest.

Since start-up the project has shipped more than 2,000 cargoes in total, according to bp’s country head.

Train 3 arrived late. It was meant to start in late 2019 but only shipped its first cargo on 18 October 2023, after the Saipem, Chiyoda and Tripatra joint venture handed it over in August. The expansion also included two offshore platforms, 13 new production wells and a new LNG loading facility. bp said three-train output would reach about 2.1 billion cubic feet of gas a day and that Tangguh would supply over a third of Indonesia’s gas production.

The domestic customer shaped the deal. PLN was Train 3’s foundation buyer, and Tangguh’s supply to Indonesia keeps rising: bp delivered 85 domestic cargoes in 2025 and expects 89 in 2026, about 71 percent of the country’s domestic LNG demand. Indonesia as a whole expected about 250 LNG cargoes in 2024, up from 213 in 2023, thanks largely to Train 3, with roughly two-thirds still exported.

The partners have since committed more capital to keep the trains full. In December 2022 the government extended the production-sharing contract by 20 years to 2055, and in November 2024 bp, which holds 40.22 percent, and its partners approved the US$7 billion Ubadari, CCUS and Compression project. It aims to unlock about 3 trillion cubic feet of gas from 2028 and to store around 15 million tonnes of CO2 in its first phase, Indonesia’s first large-scale carbon capture project.

02 · Timeline

Key moments

  1. Trains 1 and 2 begin operating

  2. Final investment decision on Train 3

  3. Production-sharing contract extended by 20 years to 2055

  4. First Train 3 cargo sails for PLN

  5. Train 3 reaches full capacity

  6. US$7 billion Ubadari, CCUS and compression project approved

03 · Exhibit
Exhibit 1 · Tangguh LNG liquefaction capacity
million tonnes a year7.6Trains 1 and 2 (2009)3.8Train 3 (2023)11.4Total after expansion

11.4 mtpa is about 180 cargoes a year. Train 3 reached full capacity in April 2024. Sources: bp; S&P Global Commodity Insights.

04 · Core tensions

The trade-offs at the heart of the case

What a foundation buyer buys

A buyer committing early helps a developer support financing even if another buyer might later offer a higher spot price. The value of that commitment depends on the agreement’s volume flexibility, delivery point and treatment of unavailable cargo. Public announcements about a customer do not establish a confidential take-or-pay formula. The seller needs room to accommodate maintenance and upstream variability. Selling every potential tonne at a fixed date can turn a small production problem into a costly replacement purchase. On the other hand, reserving too much capacity for spot sales leaves the fixed costs of the train exposed to price weakness. Revenue stability is particularly valuable when debt service falls due independently of cargo prices.

Read one clause as if a cargo were late

Choose a contract delivery window and ask the commercial and operations teams to describe the consequences of loading after it. The answers should agree on replacement, diversion rights and who owns the gas at the relevant point. A domestic foundation buyer can make the expansion easier to finance while retaining rights that limit lucrative sales elsewhere. The investor needs the value of that dependable commitment and the cost of flexibility surrendered in exchange.

Why trains are added rather than built alone

Adding a train to an existing LNG plant is usually cheaper than building a new plant, because storage tanks, jetties, power and the workforce can be shared. The catch is that the new train depends on the same gas fields and the same loading facilities as the old ones. If gas supply falls or a shared facility fails, all three trains can suffer at once. That is why the partners’ later investment in new gas supply from the Ubadari field matters as much to Train 3’s value as the train itself.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    How many tonnes can be promised without relying on perfect uptime?

  2. Q2

    Which party bears freight and replacement risk?

  3. Q3

    When does selling more output forward threaten liquidity?

  4. Q4

    Which delivery clause is most valuable to the foundation customer?

  5. Q5

    When does a replacement cargo have little commercial value?

Frameworks worth applying
  • Foundation customers in project finance
  • Take-or-pay contracts
  • Shared-infrastructure risk
  • Domestic market obligations
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

A foundation buyer like PLN was worth the price because it made a delayed, expensive train financeable and politically secure. But the investors should judge the deal over the field’s life, not the train’s: the real commitment is to keep three trains supplied with gas through 2055, which is why the Ubadari and CCUS investment followed.

  1. Lock in an anchor buyer

    Sign a domestic foundation customer to secure financing and approvals.

  2. Keep flexibility in volumes

    Leave room for maintenance and upstream shortfalls in cargo commitments.

  3. Invest to sustain supply

    Fund new fields and compression to keep all trains full.

What this plan gives up

A large domestic commitment secures approval and financing but reduces exposure to higher export prices.

The strongest counter-argument

Selling more cargoes into the domestic market at regulated prices leaves value on the table compared with export spot prices, especially in tight global markets like 2022.

Metrics to watch

  • Cargoes delivered against the 180-a-year capacity
  • Ubadari first production in 2028
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.