Case study · BangladeshEnergy and utilities2003–2018Last reviewed 22 November 2026

Bangladesh case studiesAsia-Pacific case studies

Infrastructure Development Company Limited

How IDCOL sold rural lighting one instalment at a time

A solar panel sold with no service agreement is an appliance. A panel sold on instalments with local repair support is also a credit product and a promise about future light. Bangladesh’s solar home systems programme, led by IDCOL and delivered through partner organisations, combined those elements for rural customers. Over roughly fifteen years beginning in 2003, the programme sold more than 4.1 million systems. The World Bank estimated that they served about 20 million people.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Solar home system programme began2003
Systems sold through 2018Over 4.1 million
People receiving electricity services in the World Bank accountAbout 20 million
01 · The situation

What happened

The programme’s design matters as much as its scale. Partner organisations sold and serviced systems, while financing and smaller grants supported affordability. The World Bank’s historical account describes consumer repayment over periods of up to three years and grants falling from about 19 percent of cost in 2003 to 5 percent by 2017. A smaller grant per installation can stretch a public budget. It can also exclude households with the weakest ability to make a deposit.

A household comparing a system with kerosene or other lighting sources cares about monthly cash payments, reliability and what the system can power. A lender cares about repayments after the installer has left. A technician who cannot obtain a replacement component can turn a sound loan into arrears because the family has lost the service for which it agreed to pay. Loan performance and technical performance therefore need to be examined together.

Grid expansion changes both the household’s alternatives and the dealer’s incentive to maintain older installations. A family might still value backup lighting after a connection arrives, though its willingness to continue paying the original instalment may change. The right expansion rule should combine expected grid arrival, service capacity and repayment evidence by installation cohort. Counting historical systems sold is useful for understanding reach. Sustained working systems and evenings of lighting are better measures of what families ultimately bought.

IDCOL’s solar home system programme began in 2003, with support from the World Bank and other development partners. Partner organisations, mostly NGOs and microfinance institutions, sold systems to rural households on credit, installed them and provided after-sales service, while IDCOL supplied refinancing, grants and technical standards.

According to the World Bank’s 2021 study Living in the Light, more than 4.1 million systems were sold and supported through 2018, bringing electricity services to about 20 million people, roughly 14 percent of Bangladesh’s population at the 2011 census. The study described it as the largest national off-grid electrification programme in the world.

Sales peaked at more than 860,000 systems in 2013 and then fell sharply as the national grid reached more villages, according to reporting on the World Bank study. Installations under the programme ended in 2018.

The programme offers a wider lesson for any business built around a temporary gap in public services. Demand can grow very fast and then disappear when the gap closes. Lenders and suppliers who plan for this, by keeping loan terms short, building service networks that can support new products, and preparing for falling sales, are better placed than those who assume growth will continue. The same thinking applies to many fintech and off-grid businesses today. It is also a reminder that the end of a product is part of its life cycle, and that planning for decline, including battery disposal and customer support, is a real cost that belongs in the original business case.

02 · Timeline

Key moments

  1. Programme began.

  2. Annual system sales peaked according to the World Bank.

  3. Cumulative sales exceeded 4.1 million.

03 · Exhibit
Exhibit 1 · Bangladesh: Rural access to electricity
% of rural population40.0201048.1201481.32018

Source: World Bank, World Development Indicators (EG.ELC.ACCS.RU.ZS).

04 · Core tensions

The trade-offs at the heart of the case

Open the oldest service file

Pick a district with several sales vintages and trace a sample from the original sale to the last repair, payment and working installation. Include customers who stopped paying or moved, because they are precisely the ones a sales register tends to lose. Compare the cost of a shared repair route with continuing to dispatch technicians from each dealer. My preferred expansion would fund service where the repair backlog threatens otherwise sound systems, even if that produces fewer new sales this year. If grid arrival has changed the appropriate service, explore use as backup and price it at what the household will actually pay. An installation that remains in household records after its battery fails deserves a repair decision and a different status in the programme’s performance figures.

The customer’s option to leave has a price

The mini-grid case shows the consequences of selling power in a place that eventually obtains a national connection. A home system changes that transition because the appliance can continue to serve a household separately, be used as backup or lose most of its value when a battery ages. An installer’s contract should provide an understandable service arrangement in each case. If a customer has an affordable option to keep the system working, the original sale may continue to deliver value long after grid arrival. If disposal or replacement becomes costly, apparent programme success at installation can conceal a later liability. Ask who owns the equipment and who pays for its last service visit before using sales records to project lifetime benefits.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    Who should bear the cost of servicing older systems?

  2. Q2

    How would grid arrival change repayment behaviour?

  3. Q3

    What evidence distinguishes a sale from sustained electricity access?

Frameworks worth applying
  • Consumer finance
  • Off-grid energy
  • Market building
  • Product life cycle
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

We think the solar home system programme succeeded because it treated electricity as a financed purchase, not a giveaway. Small loans, quality standards and local sellers made systems affordable; the hard lesson came later, when grid expansion cut demand and left lenders and suppliers with a shrinking market.

  1. Plan for the grid’s arrival

    Build exit and upgrade paths for customers when the grid reaches them.

  2. Support after-sales service

    Keep batteries and repairs available so existing systems keep working.

  3. Recycle batteries safely

    Fund collection and recycling as systems reach the end of their lives.

What this plan gives up

Continuing to support a declining product costs money, but stopping too abruptly can strand customers with broken systems and unpaid loans.

The strongest counter-argument

Grid electricity is cheaper and more powerful, so a fast decline in solar home systems may simply be a sign of success, and resources should move quickly to new uses such as solar irrigation and mini-grids.

Metrics to watch

  • Loan repayment rates in the remaining portfolio
  • Systems still in working order
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.