A grid pole is nearby. Why is the house still unconnected?

A power line passing a house makes a household appear well served on a regional map. The last stretch requires a connection, interior wiring and an ability to pay for the electricity subsequently used. A household may value light while being unable or unwilling to pay the full connection charge at once.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

01 · The situation

What happened

A power line passing a house makes a household appear well served on a regional map. The last stretch requires a connection, interior wiring and an ability to pay for the electricity subsequently used. A household may value light while being unable or unwilling to pay the full connection charge at once.

Researchers randomized grid expansion and varied connection offers in rural Kenya. They measured demand at different prices, actual construction costs and household outcomes after electrification. This is an unusually direct comparison between how much it cost to deliver a connection and what households were willing to pay under the conditions offered.

Demand fell sharply with the connection price. Average electricity use was low among many newly connected households, and the study did not detect broad near-term gains across its main household outcomes. That result leaves open questions about longer time horizons, reliability and complementary investments. A pole, a connection and a productive use of power are different things to count.

Kenya created the Rural Electrification Authority in 2007 to speed up access in rural areas. It first prioritised public facilities such as market centres, secondary schools and health clinics. Households within 600 metres of a transformer could apply for a connection, but the standard price was out of reach for most rural families, and the national household electrification rate stood at around 32 percent at the time of the study.

Researchers worked with the Rural Electrification Authority and Kenya Power in 150 randomly selected transformer communities in Busia and Siaya counties, covering 2,289 unconnected households. Before the study, most of these households used kerosene for lighting and spent an average of US$5.55 a month on energy.

Demand fell sharply as the price rose. Almost all households connected when the offer was free, but only a small minority did so at the full price. Experimental variation in the number of connections also showed large economies of scale: connecting many households in one area was much cheaper per household than connecting a few.

The researchers concluded that, in the medium term, the costs of connecting households were well above the benefits they could measure. They highlighted that credit constraints, bureaucratic delays, low reliability and leakage may also have reduced demand.

Kenya later launched the Last Mile Connectivity Project to connect more households at a reduced fee, financed in part by development partners, showing how the policy debate evolved.

The study’s supply-side findings are as important as its demand results. Because the cost per connection falls sharply when many neighbours connect at once, mass connection drives can be far cheaper than connecting households one by one on request. That is a classic feature of a natural monopoly, where a single network serves an area most efficiently.

Reliability also shapes demand. Households that experience frequent outages may doubt the value of paying for a connection, and businesses cannot rely on power for productive work. Investments in network quality can therefore raise the return on connection subsidies.

Off-grid solar has grown rapidly in Kenya in parallel, offering lighting and phone charging at much lower upfront cost. For many rural households, a solar home system may meet immediate needs while grid access expands over time.

For a finance student, the case is a clear application of cost-benefit analysis to infrastructure: comparing the full cost of a connection with the measurable benefits over a realistic time horizon.

Kenya’s household electrification rate has risen substantially since the study, through a combination of grid expansion, subsidised connections and off-grid solar, showing that policy can close access gaps when several tools are used together.

Those combined approaches remain a model for other countries with large rural populations still lacking power.

For households, the decision to connect resembles any investment with a high upfront cost and uncertain future benefits.

02 · Timeline

Key moments

  1. Kenya creates the Rural Electrification Authority.

  2. Randomised connection offers in 150 communities in Busia and Siaya.

  3. Results published in the Journal of Political Economy.

03 · Exhibit
Exhibit 1 · Household take-up of grid connections by price offered
percent of households95.0Free23.7US$1717.2US$2841.3US$398 (full price)

Source: Lee, Miguel and Wolfram, Journal of Political Economy (2020), as reported by the authors.

04 · Core tensions

The trade-offs at the heart of the case

Reading the result

A grid connection is a one-time change in access, whereas electricity use recurs. Make two columns for a household. Put wiring, connection charges and ready-to-use appliances in the first. Put fuel displaced, electricity consumed and interruptions in the second. A nearby pole removes only some of the first set of costs. For a planner, the construction cost per household offered service can differ sharply from the cost per active account when take-up is low. Both numbers need the same time horizon and an explicit definition of an active user.

The financing decision

Compare lowering an initial connection charge with improving reliability for households already connected. A promising result on applications does not settle how much electricity households will use or whether businesses change their hours. Follow metered use and relevant household activities separately.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    Which people would be missed by measuring only new connections providing sustained useful service?

  2. Q2

    Who carries the cost of last-mile construction, wiring and recurring charges?

  3. Q3

    What could the evidence on consumption and reliability after connection change?

Frameworks worth applying
  • Natural monopoly
  • Price elasticity
  • Infrastructure economics
  • Cost-benefit analysis
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

We think the study shows that the hardest part of rural electrification is the final connection, not the line along the road. Prices well below cost are needed to connect most households, so governments should weigh connection subsidies against reliability, appliance finance and off-grid alternatives.

  1. Subsidise the last mile

    Lower connection fees for poor households.

  2. Plan for usage

    Support affordable appliances and productive uses.

  3. Compare options

    Weigh grid connections against solar home systems.

What this plan gives up

Mass connections lower cost per household but may bring few short-run benefits if use stays low.

The strongest counter-argument

Others argue electricity’s benefits appear over decades and short studies understate them.

Metrics to watch

  • Average monthly use per new connection
  • Cost per connection
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.