Case study · BangladeshTransport and logistics2021–2024Last reviewed 22 November 2026

Bangladesh case studiesAsia-Pacific case studies

Chittagong Port Authority and RSGT Bangladesh

At Patenga, whose stopwatch measures terminal performance?

A vessel waiting outside port and a container sitting inside the yard both make customers wait. At Patenga the contract assigns different parts of that journey to different organisations. Bangladesh’s PPP Authority described marine operations as the port authority’s responsibility, with the terminal operator responsible for shore operations, including ship-to-shore transfers. A single measure of vessel turnaround could penalise one party for time controlled by the other.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Project approved in principleMarch 2021
Concession contract signedDecember 2023
Concession length reported by the operator’s shareholder22 years
01 · The situation

What happened

The project received approval in principle in March 2021. The authority signed with RSGT Bangladesh on 6 December 2023, and the operator’s shareholder reports that operations began in 2024 under a 22-year concession. A concession of this length makes equipment maintenance and handback condition consequential. A crane can be productive for years and still leave its next owner a substantial overhaul bill.

Track waiting for a berth separately from time alongside, and separate crane activity from periods when the operator cannot work because the vessel or cargo documentation is unready. From the customer’s perspective the entire wait still counts. A port needs both an end-to-end service measure and an agreed record of the cause of delays. Without the first, both organisations can meet their targets while customers wait. Without the second, a penalty may reward the party best placed to assign blame.

An operator might ask for more yard equipment while a freight forwarder asks for longer gate hours. Either could be right. If trucks arrive in bunches and cargo cannot leave overnight, faster unloading may fill the yard earlier and slow subsequent ships. Compare the change in container dwell time with the change in crane moves, and identify how much inventory value is released to traders. A public authority can negotiate performance incentives around that evidence while retaining responsibility for navigational access.

Red Sea Gateway Terminal International, through RSGT Bangladesh, signed a 22-year concession with the Chittagong Port Authority on 6 December 2023 to equip, operate and maintain the Patenga Container Terminal. Reports described the terminal, built by the port authority, as a US$240 million facility, and RSGTI as the first foreign operator at a Bangladeshi port.

Commercial operations began on 10 June 2024, when the Maersk Davao berthed. Officials said all equipment would pass to the port authority at the end of the 22 years. The Business Standard later reported in 2025 that much of the terminal’s capacity remained underused, which shows why clear, shared measures of performance matter.

RSGT later said it had invested about US$170 million and formally launched full-scale operations. Maritime Executive reported that capacity rose from about 250,000 TEU in 2024 to about 600,000 TEU, with a target of roughly 400,000 TEU of throughput.

Terminal concessions around the world face the same issue: several parties share one process, and each can blame another for delays. Clear, shared measures make accountability possible. For shippers, every extra day a container sits at a port ties up money in stock and can mean missed sales or late penalties. For the public owner, transparent data shows whether a concession is delivering what was promised, and gives a fair basis for rewards or penalties under the contract. It also helps the port plan where to invest next.

02 · Timeline

Key moments

  1. Approval in principle.

  2. IFC was appointed transaction adviser.

  3. Contract signing preceded the operating start reported by SISCO.

03 · Exhibit
Exhibit 1 · Bangladesh: Container port traffic
million TEU per year2.3920162.9020203.352024

Source: World Bank, World Development Indicators (IS.SHP.GOOD.TU).

04 · Core tensions

The trade-offs at the heart of the case

Separate gate, crane and ship

Select a group of calls with similar vessel size and exchange volumes. For each, reconstruct berth readiness, first and last crane moves, gate availability and the time the last import container left the yard. Ask shippers to verify which delay affected delivery to their buyers. If quicker crane handling merely stores containers longer inside, the operator has improved a local measure while consuming scarce yard space. I would favour a gate-hours pilot when truck release is the bottleneck and consider another crane only when yard and landside flow can support it. The concession should reward improvements that survive the complete journey through the terminal. An operator and authority can settle this boundary in advance by agreeing who records each delay, who can challenge that record and which independent timestamp resolves an argument.

Why a longer contract does not automatically produce better service

The Laldia concession extends the port comparison by bundling design, construction, finance and operation. At Patenga the published division between marine and shore responsibilities remains central. A policymaker comparing the terms should avoid ranking the contracts solely by length or announced capital. Ask which party is responsible for each delay, who has the power to remove it and whether the public authority has retained a cost it can predict and fund. A shorter or narrower operating contract can offer strong incentives when boundaries are observable. A longer integrated agreement can be valuable when construction and operating choices must be coordinated. Neither structure will by itself make the road outside a full container yard less congested.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    Where does the concessionaire’s clock start?

  2. Q2

    What would distinguish yard congestion from weak crane productivity?

  3. Q3

    How should the agreement value maintenance near handback?

Frameworks worth applying
  • Public-private partnership
  • Performance contracts
  • Bottleneck analysis
  • Service-level metrics
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

We would measure Patenga on the time a shipper actually waits, split clearly into waiting at anchor, at the berth, in the yard and at the gate. When different organisations control each stage, one shared clock is the only fair way to see who is causing delays and whether the concession is working.

  1. Publish one end-to-end clock

    Report anchorage, berth, yard and gate times together every month.

  2. Tie payments to the operator’s own stages

    Link incentives only to the steps the terminal operator controls.

  3. Align customs and gate hours

    Extend inspection and gate hours together so longer opening actually moves boxes.

What this plan gives up

Detailed public reporting can expose weak performance early and strain the partnership just as the operator is still bringing in equipment.

The strongest counter-argument

The operator may argue that early comparisons are unfair while equipment is still arriving, and that a long 22-year concession should be judged on its overall results, not on the first few months.

Metrics to watch

  • Average vessel waiting time at anchor
  • Yard dwell time for import containers
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.