Who keeps a shared sanitation block open?

Some settlements waited for permanent housing and household connections while families still needed safe places to wash and use a toilet every day. The gap between current needs and a long-term housing plan created a municipal obligation. A completed building, however, is a poor measure of a service if its water stops or its doors stay locked.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Facilities delivered while permanent household services were pendingShared access
01 · The situation

What happened

Some settlements waited for permanent housing and household connections while families still needed safe places to wash and use a toilet every day. The gap between current needs and a long-term housing plan created a municipal obligation. A completed building, however, is a poor measure of a service if its water stops or its doors stay locked.

eThekwini installed communal ablution blocks where conditions permitted connection to waterborne services. The facilities brought together toilets and washing facilities and formed part of a wider approach to improving informal settlements. The arrangement allowed a shared service to operate while permanent housing and infrastructure followed a different timetable.

The case studies document delivery of shared facilities and their place in incremental upgrading. They establish an alternative to waiting for a household connection. They provide no single estimate here of household time saved, service hours or avoided illness. Those outcomes depend on siting, access, cleaning and continued operation at each block.

eThekwini, the municipality that includes Durban, has hundreds of informal settlements. While permanent housing and household connections are planned, the city installed community ablution blocks, many built from modified shipping containers fitted with toilets, showers, washbasins and laundry troughs.

A 2010 case study counted 108 brick blocks and 240 container blocks, serving roughly 600,000 people, with total investment of about R280 million. A pair of container blocks, including transport, site preparation and running costs, cost about R200,000.

Each facility has separate male and female units and a caretaker drawn from the community. Blocks typically serve 50 to 75 dwellings within 200 metres.

In 2015 the programme won the African Utility Week Municipality of the Year award. By 2021 the city reported 1,600 ablution facilities across 78 wards.

The approach shows how a municipality can provide basic dignity and hygiene quickly while longer-term housing programmes continue.

The design reflects practical choices. Shipping containers are durable, can be fitted out in a workshop and transported to sites, and can later be moved or reused when formal housing arrives. Each container is fitted with toilets, showers and hand basins, with a small storeroom for cleaning supplies.

Running costs are an essential part of the budget. Caretakers clean the facilities and manage opening hours, and the municipality pays for water, electricity, consumables and repairs. A study by the University of KwaZulu-Natal’s Pollution Research Group surveyed 50 sites across 31 settlements to explore the opportunities and challenges of these communal services.

Researchers have also examined the whole life cycle of the facilities, identifying technical factors that help them succeed as an interim measure in informal settlement upgrading elsewhere in South Africa.

Shared sanitation is common in fast-growing cities across Africa and Asia, and Durban’s approach is often studied by other municipalities looking for ways to provide dignified services quickly.

The programme has grown well beyond the figures in the 2010 case study. By 2015 it had been implemented in about 350 informal settlements, and a 2016 report described around 2,500 ablution blocks installed across many of the city’s nearly 500 informal settlements.

That growth illustrates a common pattern in public service delivery: once a design is proven and procurement and maintenance systems are in place, a municipality can scale up quickly. The harder challenge is keeping every facility functional, because a broken toilet or a locked door means the service has stopped even though the asset still exists.

Students can use the case to compare the cost of an interim facility with the cost of waiting for full household connections, and to think about how operating budgets should be protected when capital budgets are under pressure.

The container design also allowed the municipality to standardise procurement. Fitting out identical units in a workshop made costs more predictable and allowed the city to train contractors and caretakers using a common model across sites.

02 · Timeline

Key moments

  1. Container-based ablution block rollout accelerates.

  2. SuSanA documents 348 blocks serving about 600,000 people.

  3. Programme wins African Utility Week Municipality of the Year.

03 · Exhibit
Exhibit 1 · Communal ablution blocks in eThekwini, 2010 case study
blocks240Container blocks (Water and Sanitation Dept.)108Brick blocks (other departments)

Source: SuSanA case study of eThekwini community ablution blocks (2010).

04 · Core tensions

The trade-offs at the heart of the case

Our assessment

Cost an attendant, cleaning supplies, repairs and a reliable route for reporting problems before approving another site. Compare an extra block in an unserved area with restoring full hours at an existing one. Each can improve access, but they reach different households. An implementation account describes municipal provision for caretakers and cleaning supplies as part of operating the ablution blocks. That detail changes the interpretation of the capital expenditure. The service depends on regular, often unobtrusive work after construction crews leave. A caretaker can notice a failed tap or a shortage of paper early but still need another unit to authorize a repair or replenish stock. A follow-up visit should therefore trace one reported fault all the way to resolution. A tidy facility on inspection day is welcome, but a resolved fault shows the city can restore service after an ordinary breakdown.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    Who could be missing from the reported measure of successful visits at the times people need access?

  2. Q2

    Which part of cleaning, attendants and unplanned repairs must be financed every year?

  3. Q3

    How would evidence on interruptions reported by different groups of users affect your choice?

Frameworks worth applying
  • Interim services
  • Informal settlements
  • Operations and maintenance
  • Public health
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

We think Durban’s communal ablution blocks are a practical and dignified interim solution for informal settlements. Their success depends on caretakers, cleaning and reliable water, so the operating budget matters as much as the construction budget.

  1. Fund caretakers

    Pay community members to clean and manage blocks.

  2. Maintain supplies

    Keep water, soap and toilet paper available.

  3. Plan the transition

    Link blocks to future formal housing.

What this plan gives up

Shared facilities deliver services quickly but depend on ongoing management.

The strongest counter-argument

Some argue resources would be better spent accelerating permanent housing with household connections.

Metrics to watch

  • Share of blocks fully functional
  • Hours open per day
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.