Skip to content
All case studies
Case study · United KingdomNuclear project finance2016–2017 decisionLast reviewed 22 November 2026

United Kingdom case studiesEurope case studies

Hinkley Point C

What risk does a 35-year electricity price guarantee buy?

A 35-year price agreement helped finance Hinkley Point C. Consumer exposure still depended on when the plant generated electricity and what the wholesale market paid at the time.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

2017-review reference strike, 2012 prices, subject to Sizewell C condition£92.50/MWh
Contract term from generation35 years
2016-price construction estimate in the 2017 review£18bn
NAO review2017
01 · The situation

What happened

Hinkley Point C presented a financing challenge before it produced a unit of electricity. Investors were being asked to commit large sums to construction against revenue that would begin much later. The contract for difference offered a long period of revenue support for eligible generation. The public decision was whether the resulting reduction in electricity-price risk justified the terms agreed for consumers.

The NAO reported a £92.50 per megawatt-hour strike price in 2012 money, indexed over time, for 35 years from generation. Comparing that price directly with an unadjusted wholesale quote from a different year gives a misleading spread. The comparable reference price and the actual qualifying output determine settlement. A construction delay can defer the flow of payments while still harming a wider strategy that depends on the plant being available.

A delayed power station can reduce near-term contract settlements simply because it generates nothing. That does not make delay good news for consumers. Replacement generation may be expensive and the system may receive a different mix of dependable capacity. Draw the settlement cash flow beside the system’s generation requirement for the same years. Ask where the replacement electricity comes from, whether its cost was already in the wholesale forecast and which party bears construction expenditure in the interim. Only then can the consumer exposure be interpreted. A reduction in one line of the contract model and an increase in a different line of the power-system budget can describe the same delay.

Hinkley Point C, in Somerset, is the first new nuclear power station in Britain for a generation, with two EPR reactors designed to supply about 7% of Great Britain’s electricity. EDF is building it with China General Nuclear. In October 2013 the government agreed a contract for difference: once the plant generates, EDF will receive £92.50 per megawatt-hour in 2012 prices for 35 years, with consumers paying the difference when wholesale prices are lower and receiving it back when they are higher.

The NAO’s 2017 review put the construction cost at £18 billion in 2016 prices and the expected investor return at about 9%. Costs then rose repeatedly. In May 2022 EDF raised its estimate to £25–26 billion and delayed start-up to June 2027. In January 2024 it gave a range of £31–34 billion in 2015 prices, possibly about £46 billion in 2024 prices, with the first reactor operating between 2029 and 2031. A later revision put the cost at £35 billion with the first reactor expected in 2030.

Because EDF bears overruns, the delays mainly hurt its shareholders. But consumers are affected too: the strike price, about £129/MWh in 2024 money, is fixed, and Britain waits longer for the power. For Sizewell C, the government switched to a regulated asset base model in which bill-payers share construction risk.

Investors judge such a project on its expected return over a very long life. The NAO noted that NNB Generation Company expected net project cash flows of £79.7 billion by the end of the plant’s operating life in 2085, in 2016 prices, which shows how much of the value lies decades in the future.

02 · Timeline

Key moments

  1. The project proceeds with a long-term revenue arrangement.

  2. The NAO examines the commercial case and risk allocation.

  3. Eligible output can receive contract settlement over the agreed term.

03 · Exhibit
Exhibit 1 · Hinkley Point C: estimated construction cost
£ billion (upper end, mostly 2015 prices)182016 approval26May 202234Jan 202435Latest revision

EDF said the January 2024 range could equal about £46bn in 2024 prices. Sources: NAO (2017); Daily Telegraph via PressReader; World Nuclear News; AJ Bell.

04 · Core tensions

The trade-offs at the heart of the case

A comparison with UK offshore wind auctions: A supported price and the cost of securing an offer

A quoted price per megawatt-hour makes comparison look simpler than it is. Adjust for the price base, contract duration, expected availability, construction risk and time to first generation. For a consumer concerned with reliable supply, the generation profile matters as well. For a financier, the period between the first major expenditure and the first supported receipt can dominate the effect of a modest price difference. A procurement authority can preserve discipline by maintaining a credible alternative and by testing what it costs to wait. Running another auction has a cost if grid, port or manufacturing opportunities disappear. Signing now has a cost if future rivals could deliver comparable output more cheaply. Explicitly valuing both sides of the timing decision makes an empty round informative without granting every developer’s proposed price the status of a necessary public expense.

What to watch

A project finance lender starts by separating completion risk from operating revenue risk. A power price known in advance can support more debt once a plant is generating. It does not make concrete, commissioning or operating availability certain. Determine when lenders can first draw on the revenue promise, what counts as eligible electricity and what happens during an extended outage. Only then can the duration of the contract be translated into a dependable borrowing capacity.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    How should procurement compare projects with different expected opening dates?

  2. Q2

    What market price would make consumers receive money under a two-way settlement?

Frameworks worth applying
  • Contracts for difference
  • Construction risk
  • Cost of capital
  • Consumer vs investor risk
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

Compare alternative packages on equivalent delivery dates, dependable output and exposure to construction failure. Require decision makers to see the distribution of consumer payments under several wholesale-price paths as well as a central estimate. Show who pays for replacement electricity if construction takes longer.

  1. Fix the price, not the cost

    Guarantee £92.50/MWh (2012 prices) for 35 years from generation.

  2. Leave overruns with EDF

    Make the developer bear construction cost increases.

  3. Use a different model for Sizewell C

    Shift to a regulated asset base for the next plant.

What this plan gives up

The fixed price protected consumers from construction overruns, but it locked in a high price for 35 years and relied on private investors with a high cost of capital.

The strongest counter-argument

A shorter contract might reduce the period of consumer exposure and raise the price investors require for financing. A public buyer willing to bear wholesale-price risk can do so more cheaply in some circumstances. The challenge is demonstrating that the benefit was reflected in the agreed strike and not absorbed entirely in the investors’ return.

Metrics to watch

  • First-unit start date
  • Wholesale prices vs the strike price
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.