What happened
AES Andes announced commercial operation in July 2023. It described 180 MW of solar panels and a battery rated at 112 MW for five hours. Multiplying the latter two figures gives 560 MWh of nominal discharge capability at rated power under the stated design. Adding the solar and battery ratings and treating the total as a continuous evening supply would count a charging source as if it were a second nighttime generator.
Reconstruct one operating day. Energy that enters the battery has an opportunity cost whenever it could have been sold directly. To deliver a specified quantity later, the operator must charge more energy than it ultimately sells because the cycle has losses. Battery ageing, temperature and reserve commitments can reduce usable output. Grid connection limits may bind before either nameplate rating is reached. The highest-price hour is irrelevant if the store is empty when it arrives.
AES Andes, the Chilean subsidiary of the US company AES, built Andes Solar IIB in the Antofagasta region. It announced commercial operation in July 2023.
The project combines 180 MW of solar panels with a battery able to discharge 112 MW for five hours, or about 560 megawatt-hours of storage at rated power.
Northern Chile has abundant sunshine, so solar plants produce large amounts of electricity in the middle of the day. Prices at those hours can fall very low, sometimes to zero, while evening prices remain higher.
Batteries allow solar plants to store midday output and sell it later, earning more per megawatt-hour and reducing curtailment.
The economics depend on several factors: the cost of the battery, how many times it can be charged and discharged, how quickly its capacity declines and the size of the price gap between charging and discharging hours.
Adding storage to an existing solar site can reuse land, grid connections and permits, which lowers the cost compared with building a separate project.
Chile has since seen rapid growth in battery projects, encouraged by the large amount of solar power that otherwise goes unused.
Similar solar-plus-storage projects have spread in California, Australia and the Middle East, where solar output is also concentrated at midday.
Battery capacity declines with use. After thousands of charging cycles, a battery can store less energy than when it was new. Operators must decide whether to replace cells or accept lower capacity, and that decision affects long-term returns.
Revenue can come from several sources: shifting energy from low-price to high-price hours, providing services that help keep the grid stable, and receiving capacity payments for being available when needed.
As more batteries are built, the difference between midday and evening prices may narrow, reducing the profit from energy shifting. This is known as cannibalisation and also affects solar plants.
Chile’s regulators have been updating market rules to recognise the value of storage, which affects how batteries are paid.
For students, the case is a practical example of unit economics: the profit per megawatt-hour cycled must cover the cost of the battery over its life.
The project shows how storage is becoming a standard part of solar development in Chile rather than an experimental addition.
AES Andes has also invested in other solar, wind and storage projects as it shifts away from coal.
The project’s operating data will help investors judge how much value batteries add in Chile’s market.
Those results also influence how banks assess the risk of lending to future storage projects.
Other developers have since announced large battery projects in northern Chile, many paired with existing solar plants.
That growth may eventually reduce the price differences that make storage profitable, which is why early projects such as Andes Solar IIB are closely studied.
Key moments
The array can supply electricity to the battery.
AES Andes announces commercial operation of the combined installation.
Source: AES Andes, cited in the case. At five hours, the battery holds about 560 MWh (simple arithmetic).
The trade-offs at the heart of the case
Two ways to move desert sunlight into the evening
Cerro Dominador stores heat before making electricity, while Andes Solar IIb pairs photovoltaic generation with a battery. The two facilities cannot be compared by dividing their capital budgets by a single solar megawatt figure. Trace one unit of sunshine through the energy conversion chain, measure losses and determine the hours for which delivery can be promised. A five-hour battery can be a better match for a narrow evening peak even if a thermal store lasts longer. A long sequence of valuable hours may favour a different design. Both face the possibility that more storage will flatten the very evening premium that underpins their economics. The correct benchmark is the least-cost feasible way of meeting the same delivery obligation, at the same location, with the same allowance for shortfall and degradation.
Our assessment
I would compare actual dispatch with a feasible alternative that has the same solar generation and connection rights. Credit the battery for incremental gross margin after charging costs and degradation. Test a future with more competing storage. If other batteries make midday power more valuable and evening power cheaper, both sides of the price spread can move against the investment. A firm delivery contract can protect part of the margin while adding exposure to shortfalls.
For your seminar, paper or interview
- Q1
When is curtailed solar energy genuinely available at zero opportunity cost?
- Q2
How much charging energy would be needed to deliver a full rated cycle?
- Q3
Which contract term protects value if the evening peak becomes shorter?
- Q4
Would paying to accelerate construction recover a full year of receipts or only change their timing?
- Battery storage
- Solar power
- Energy arbitrage
- Grid flexibility
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
We think Andes Solar IIB shows how batteries can turn cheap midday solar power into electricity available in the evening. Its value depends on the price difference between day and night, which can shrink as more storage is built.
Track price spreads
Monitor day–night price differences.
Contract revenues
Sell storage under long-term agreements.
Manage degradation
Plan for battery capacity loss.
What this plan gives up
Storage adds flexibility but its revenue depends on price gaps.
The strongest counter-argument
Some argue storage will be built faster than demand for it grows.
Metrics to watch
- Battery cycles per year
- Evening electricity prices
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- AES Andes · Andes Solar IIb commercial operation ↗
- AES Chile · Project specifications ↗
- Photo: Atacama Desert between Antofagasta and Taltal by Valerio Pillar, CC BY-SA 2.0 (cropped and resized) ↗
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.