What happened
ADB described Sarulla as three generating units supplied from two reservoir areas in North Sumatra under a thirty-year energy sales contract with PLN . Sponsor ITOCHU reported the first unit in commercial operation in March 2017 and described the three-unit scheme at approximately 330 megawatts . ADB’s appraisal used about 320 megawatts. The difference between appraisal and sponsor descriptions is a reason to keep their figures in context, particularly when comparing capacity with actual annual sales.
ITOCHU announced commercial operation of the final unit in May 2018, following the first unit’s commercial start in March 2017 . The phased record matters to a financier because one unit can produce revenue while another still carries completion risk.
Sarulla took more than two decades to reach construction, held back by bureaucracy and a lack of finance, before groundbreaking in June 2014. The sponsors included Japan’s ITOCHU and Kyushu Electric with 25 percent each and the US developer Ormat with 12.75 percent. A lending group led by the Asian Development Bank and the Japan Bank for International Cooperation agreed to provide up to about US$1.2 billion of loans towards about US$1.6 billion of project costs, roughly US$5 million per megawatt, only after the sponsors and lenders agreed many risk-mitigation measures.
The resource itself was strong. Wells at the field reportedly produced fluids hotter than 260°C, up to 276°C, and the discovery was estimated at about 330 MW. The Climate Policy Initiative found that Sarulla delivered power at a cost comparable with geothermal projects elsewhere, but still 40 to 60 percent more expensive than coal in Indonesia if emissions and health costs are ignored. That gap is why concessional finance and a long-term contract with PLN mattered.
Indonesia’s wider programme has moved more slowly than its plans. The government once targeted 7.2 GW of geothermal by 2025. Actual capacity was about 2,131 MW in early 2021, 2,356 MW at the end of 2022 and about 2,598 MW at the end of 2023, still second only to the United States. The country now aims for about 5.8 GW by 2030, and has tried government-funded exploration drilling to take early resource risk off private developers.
Key moments
Sarulla concession first awarded; project stalls for years
Groundbreaking after financing is agreed
First unit enters commercial operation
Third and final unit enters commercial operation
Indonesia’s geothermal capacity reaches about 2,598 MW
Sarulla’s 330 MW alone added about 20 percent to Indonesia’s geothermal capacity when complete in 2018. Sources: ThinkGeoEnergy citing EBTKE; Wikipedia; Stanford Geothermal Workshop (2025) citing MEMR; Climate Policy Initiative.
The trade-offs at the heart of the case
Two risks with different owners
A long-term purchase agreement can make the price of accepted electricity more predictable. It does not manufacture steam. Asking the purchaser to cover every failed development expenditure may allow development to proceed while weakening the incentive to investigate cheaper alternatives. Putting all early uncertainty into senior debt can create the opposite problem. A promising site can fail because the borrower runs out of cash before learning whether it works. Stage the financing around information. Equity or exploration support can bear the initial uncertainty. Debt can enter against evidence of sustainable production and a credible cash-flow contract. A developer may object that delaying a turbine commitment sacrifices delivery dates and discounts. Compare those costs with the loss on equipment bought for output the reservoir cannot sustain. The cheap order is expensive if it commits the whole project too early.
Define the next irreversible cheque
Stage the recommendation around the information available immediately before drilling the next well. If the test is favourable, state what capacity the operator can actually commit to sell. If it is disappointing, identify the expenditure that can still be cancelled and the work needed to leave the site in an acceptable condition. A test creates financial value only when somebody can act differently after seeing the result. Spending already incurred belongs outside that comparison.
Why geothermal is hard to finance
Geothermal projects front-load their risk. A developer must spend heavily on drilling before it knows how much steam a field can sustain, and a dry or weak well can cost millions with nothing to show. Once the field is proven, however, a geothermal plant can run around the clock for decades with no fuel bill. That profile suits equity and public exploration funds early and cheap long-term debt later. Lenders who are asked to take the early risk demand high returns or refuse, which is one reason Indonesia has developed only a small share of the geothermal potential it is believed to have.
For your seminar, paper or interview
- Q1
Who bears a loss if the reservoir cannot support contracted output?
- Q2
Which commitments can safely be deferred until after testing?
- Q3
How would a tighter financing deadline change the value of waiting?
- Q4
What decision changes after a disappointing well test?
- Q5
When could better gathering efficiency produce no additional sales?
- Staged financing under resource risk
- Risk allocation in project finance
- Real options
- Public support for exploration
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
Stage the money around the evidence. Equity, grants or government drilling should pay for proving the steam; senior lenders should come in only once sustained flow is demonstrated. Sarulla worked because its sponsors and lenders spent years agreeing exactly that kind of risk split, and Indonesia’s slow progress since shows how rare such agreements remain.
Fund exploration with risk capital
Use equity, grants or state drilling for the first wells.
Bring in debt on proven flow
Lend against tested, sustained production and a signed tariff.
Keep turbine orders flexible
Order generating units in stages that match proven steam.
What this plan gives up
Staging protects lenders and taxpayers from dry wells but delays first power and can raise equipment costs.
The strongest counter-argument
Splitting finance into stages adds time and transaction cost, and turbine suppliers may charge more for later orders, so a single upfront commitment can be cheaper when the geology is already well understood.
Metrics to watch
- Plant availability and steam output per unit
- Progress of government-funded exploration drilling
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- Asian Development Bank: Sarulla project appraisal ↗
- ITOCHU: final unit enters commercial operation ↗
- Power Magazine: Sarulla comes alive with private finance ↗
- Climate Policy Initiative: Sarulla case study ↗
- Indonesia Investments: Sarulla’s capacity rises ↗
- Stanford Geothermal Workshop 2025: Indonesia capacity ↗
- ThinkGeoEnergy: Indonesia country profile ↗
- Image: Geothermal pipes at Dieng in Central Java illustrate the gathering infrastructure used in the industry. Sarulla is in North Sumatra. Photograph credit: Haridi123. Original photograph · CC BY 4.0. ↗
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.