What happened
The first valuation question concerns ordinary wholesale demand. A domestic provider needs an international route, inland transport, equipment and customers willing to pay. An international circuit can be available at the shore while an inland link remains a bottleneck. A sales team may sell less bandwidth than the system could technically carry. Prices can fall as traffic grows. A positive traffic forecast therefore does not translate one for one into revenue growth.
The second valuation question concerns resilience. An internet provider may pay for a path it rarely uses because it lets it keep serving customers when the main route is unavailable. To sell that protection the two paths must remain independent where failures matter. A second ocean cable that feeds into the same vulnerable inland connection provides less effective diversity than a route map suggests. Service agreements must specify how much capacity can be restored simultaneously when several customers call on their backup.
Compare contracts that sell dedicated standby capacity with contracts that promise shared restoration. Dedicated capacity commands a stronger promise and leaves less available for regular sale. Shared restoration can improve utilisation but creates competing claims during a major outage. A board should ask its wholesale team for revenue by contract type and its operations team for tested restoration performance under simultaneous demand. The easiest capacity to sell twice is also the easiest capacity to promise twice.
Bangladesh signed an MoU with the SEA-ME-WE 5 consortium in December 2011 and joined it in March 2014. Local reports put the cost of joining at about Tk 660 crore. The cable linked South-East Asia, the Middle East and Western Europe, with a landing station built at Kuakata in Patuakhali.
Bangladesh was connected to the cable on 21 February 2017, and the landing station was formally inaugurated on 10 September 2017. BSCCL said the link would start at about 200 Gbps and rise in stages to 1,500 Gbps, out of a total system design capacity of 24 Tbps.
At the time, the country was using a little over 400 Gbps of international bandwidth, much of it imported over terrestrial links from India, and its only other submarine connection was SEA-ME-WE 4. Industry voices quoted in the Dhaka Tribune argued that selling the new capacity would need more business-friendly pricing.
The broader lesson is about how to value spare capacity. A backup that is rarely used can look like waste in normal times, yet it protects against losses that would be very large if the main route failed. Businesses face the same choice with backup suppliers, standby generators and cash reserves. The right question is not how often the backup is used, but how much a failure would cost and how much the backup reduces that cost. Seen that way, a second cable can be cheap insurance rather than an idle asset.
Key moments
The company joined the SEA-ME-WE 5 consortium.
The Kuakata connection was commissioned according to the directors’ report.
The commercial inauguration followed.
Source: World Bank, World Development Indicators (IT.NET.USER.ZS).
The trade-offs at the heart of the case
Test the bad day, together
Ask customers to specify how much capacity they expect to reclaim during a common interruption. Add the requests for the same failure scenario and compare the sum with independently routed, usable capacity. A small restoration test for one customer may succeed even when the full book of promises cannot be honoured. I would sell explicit classes of protection and price them according to the resources reserved, with disclosure of priorities during an interruption. Premium fees are credible when the provider can demonstrate tested service. Otherwise attractive backup revenue can be an unrecognised liability to all the customers who will request the same capacity at once. The clearest evidence of a successful second route would be an independently timed restoration exercise that holds both the international segment and the domestic segment to the service sold to the final customer.
Two international links, two kinds of spare capacity
The Bheramara electricity interconnection offers a useful parallel. Both networks sell access to an international flow constrained by physical capacity. A power buyer without an energy purchase agreement can have unused transmission space; an internet provider without independent inland backhaul can have a second ocean route that fails to restore service. In each market a local contract must meet the international asset at the right place and time. The products differ in a crucial way. A bandwidth customer may value a standing reservation even when it rarely carries traffic. An electricity buyer must also secure an energy source and settle the actual units delivered. A useful investment memo prices the relevant reservation and the cost of using it separately.
For your seminar, paper or interview
- Q1
How much of the design belongs to the Bangladesh operator?
- Q2
How would a shared inland bottleneck affect backup value?
- Q3
When is idle bandwidth an economically productive asset?
- Redundancy value
- Capacity planning
- Network resilience
- Real options
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
We would value the second cable mainly as insurance, not as extra bandwidth. Its biggest payoff comes on the rare days when the first route fails, so BSCCL should be judged on how much traffic it can keep online during an outage, not only on how much capacity it sells in a normal month.
Run joint outage drills
Test, with operators, how quickly traffic can switch from one cable to the other.
Price standby capacity
Offer cheaper backup contracts so operators pay to keep a route ready.
Plan domestic backhaul early
Make sure inland links from the landing station can carry the full load.
What this plan gives up
Selling spare capacity cheaply raises revenue now but can leave too little headroom if a cable cut forces all traffic onto one route.
The strongest counter-argument
Terrestrial links through India and private cables may already provide enough backup, so heavy investment in standby capacity on a state cable could duplicate options the market is already supplying.
Metrics to watch
- Time to restore traffic after a cable fault
- Share of BSCCL capacity actually sold
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- Bangladesh Submarine Cables: Directors’ report, SMW5 capacity ↗
- The Daily Star: Commercial inauguration and bandwidth, September 2017 ↗
- SEA-ME-WE 5 consortium: Original system design fact sheet ↗
- The Daily Star: Initial connection and domestic backhaul, February 2017 ↗
- World Bank: World Development Indicators, Individuals using the internet ↗
- BSCCL: Annual report (directors’ report) ↗
- bdnews24: PM opens second submarine cable landing station ↗
- Dhaka Tribune: Connected with second submarine cable ↗
- SEA-ME-WE 5: Fact sheet ↗
- Dhaka Tribune: Selling bandwidth from SEA-ME-WE 5 ↗
- Photo: Kuakata SeaBeach.jpg by ArifHossainFC, CC BY-SA 4.0 (cropped and resized) ↗
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.