What happened
The transport ministry records that klia2 opened on 2 May 2014, that operations moved from the former low-cost carrier terminal on 9 May, and that its design capacity was 45 million passengers annually. Malaysia Airports’ 2014 report distinguishes klia2 from the old terminal when describing traffic that year and reports over 80 million passengers for the wider airport group. Group traffic, terminal capacity and people who pass a particular shop are three different denominators.
Malaysia Airports’ report groups the former LCCT and klia2 when describing 2014 traffic across the operating transition. For a commercial tenant forecasting footfall, the transfer week needs explicit treatment. A full calendar year of system traffic is a poor starting denominator for a facility opened in May.
klia2 was announced in 2007 as a replacement for the old low-cost carrier terminal at a cost of RM1.7 billion. The estimate rose to RM2 billion in 2009 and RM2.5 billion in 2010, and Parliament was told in October 2012 that the cost had reached RM4 billion. Malaysia Airports Holdings (MAHB) attributed much of the rise to an enlarged scope, such as a fully automatic baggage handling system, and the transport ministry later said the project had never had a cost overrun because the scope had changed. A parliamentary Public Accounts Committee investigated and criticised MAHB for not addressing the concerns of its main user, AirAsia.
The opening was postponed five times before klia2 finally opened on 2 May 2014, with airlines moving across from the old terminal on 9 May. It was described as the world’s largest purpose-built terminal for low-cost carriers, with capacity for 45 million passengers a year. In its first weeks it handled more than two million passengers. AirAsia moved reluctantly, citing operational and safety concerns, and later sued the operator over losses linked to water pooling on aprons and parking bays.
The tension at the heart of klia2 was commercial. A low-cost airline wanted cheap charges and fast turnarounds. The airport operator, which earns much of its income from retail and parking, designed a larger terminal with longer walks past shops. Each side’s business model pulled the design in a different direction.
Key moments
klia2 announced at RM1.7 billion
Parliament told the cost has risen to RM4 billion
Opening date delayed five times
klia2 opens
AirAsia and other airlines move from the old LCCT
AirAsia sues the airport operator over losses from apron problems
Cost estimates as reported; the transport ministry attributed the rise to an enlarged scope. Sources: Yahoo News Malaysia; The Edge; The Star.
The trade-offs at the heart of the case
A commercial square metre has two customers
A concessionaire buys access to people likely to purchase something. An airline buys enough gate, baggage and passenger capacity to dispatch a flight reliably. Some space serves both purposes. A convenient coffee stand near a waiting area can improve the experience without altering the route. A retail detour at a bottleneck is different. Its hidden cost may appear in an airline’s operating account as delay rather than in the landlord’s property account.
What the airline should ask of the landlord
Pick one departure bank and trace its final passengers through the terminal. Where do they spend money willingly, and where does the layout merely compel them to walk farther? A lease whose rent rises with genuine additional sales can align incentives if the landlord also bears a consequence for avoidable gate delay. The concessionaire, airport and airline should be able to agree on how one late boarding is recorded before bargaining over the next square metre of shop space.
For your seminar, paper or interview
- Q1
Which passengers are realistic retail customers?
- Q2
How could a lease shift delay costs onto an airline?
- Q3
What observation would justify a shorter route to the gate?
- Q4
What changes if a tenant pays only a fixed rent?
- Q5
Which measurement would reveal a bottleneck caused by a retail detour?
- Scope creep
- Airport commercial model
- Customer-landlord relations
- Project governance
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
klia2 delivered a large, modern terminal that has served tens of millions of low-cost travellers, but its cost more than doubled and its main customer was left dissatisfied. Agreeing the design brief with the anchor airline before construction would likely have reduced both the cost growth and the conflict.
Lock the brief early
Agree capacity and design standards with anchor users before tendering.
Separate scope from overruns
Report cost changes from new scope and from inefficiency separately.
Share commercial gains
Link retail layout decisions to turnaround performance targets.
What this plan gives up
A bigger, more commercial terminal earns more retail income but raises costs and walking times for budget airlines.
The strongest counter-argument
Airport terminals are built for decades, and the larger scope may prove sensible as traffic grows. Retail income also helps keep aeronautical charges lower than they would otherwise be.
Metrics to watch
- klia2 passenger numbers against capacity
- Airline charges and service-level agreements
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- Malaysian Ministry of Transport: klia2 terminal profile ↗
- Malaysia Airports Holdings: annual report 2014 ↗
- Yahoo News Malaysia: the cost of building klia2 ↗
- The Malaysian Insight: klia2 controversies ↗
- The Star: ministry says klia2 never had a cost overrun ↗
- EdgeProp: audit on klia2 cost, capacity 45 million ↗
- The Edge: PAC criticises MAHB for ignoring AirAsia’s concerns ↗
- Image: Travellers in the klia2 international departure hall in September 2016. Photograph credit: Morio. Original photograph · CC BY-SA 4.0. ↗
Figures are as reported by the companies or cited outlets as of 25 November 2026. Check the source before quoting. Corrections: let us know through the solution form.