Skip to content
All case studies
Case study · MalaysiaFourth competitive solar round, 2021–2022Last reviewed 25 November 2026

Malaysia case studiesAsia-Pacific case studies

Energy Commission of Malaysia

Can the lowest solar bid still finance a power plant?

The cheapest tariff promises inexpensive electricity only if the winning project can reach operation. After a bid is submitted, panel prices, borrowing costs and delivery dates can change. The buyer must balance incentives to submit realistic bids against the public cost of abandoning capacity that households and businesses expected to receive.

Suggested for: MBA strategy · Corporate finance · Facts as of 25 November 2026

Capacity awarded823 MW of 1,000 MW offered
Winning bids17.68 to 24.81 sen per kWh
PPA termExtended from 21 to 25 years
01 · The situation

What happened

The Energy Commission published shortlisted bidders for the fourth large-scale solar round, LSS@MEnTARI. In August 2022 The Edge reported that project agreements were to be extended by four years, from 21 to 25, citing sources. That reporting is evidence of the proposed contractual remedy at the time. It is not a project-by-project record of which agreements were signed, which sites operated or how much electricity each generator ultimately delivered.

The regulator’s published shortlist is an award-process document. It records a procurement decision at a particular stage. The later report on contract extensions concerns financing terms. Neither document is an actual generation meter reading, and combining them does not produce evidence of electricity delivered.

Malaysia’s large-scale solar (LSS) programme awards long-term power purchase agreements (PPAs) through competitive bidding. Prices fell quickly from round to round: the lowest bid was about 39 sen per kWh in LSS1 and 33.98 sen in LSS2, before dropping to 17.78 sen in LSS3. The fourth round, LSS@MEnTARI, offered 1,000 MW in 2020 and in March 2021 the Energy Commission shortlisted 30 bidders for 823 MW, with winning prices of 17.68 to 24.81 sen per kWh.

Many bidders assumed solar module prices would keep falling. Instead, module, freight and commodity costs rose in 2021 and 2022 as China restricted exports and supply chains tightened; one report cited project prices in Europe rising from about 20 US cents a watt in July 2020 to nearly 29 cents by February 2021. Analysts warned that some LSS4 bids no longer earned an acceptable return.

In 2022 the Energy Commission extended the PPAs of all LSS4 projects from 21 to 25 years, on condition that land rights were also extended. Reports said the extra years would help restore returns to the high single digits forecast in the bids. Developers including TNB, Tan Chong, KPower and Ranhill received extensions. Later rounds kept prices falling, to about 13.75 sen per kWh in LSS5+.

02 · Timeline

Key moments

  1. LSS4 (LSS@MEnTARI) launched

  2. 30 shortlisted bidders announced, 823 MW

  3. Solar module and logistics costs rise

  4. Four-year PPA extensions reported

  5. Extensions confirmed for shortlisted projects

03 · Exhibit
Exhibit 1 · Lowest winning bid in each large-scale solar round
sen per kWh39.00LSS133.98LSS217.78LSS317.68LSS4

LSS4 winning bids ranged from 17.68 to 24.81 sen per kWh. Sources: The Edge; pv magazine; The Star.

04 · Core tensions

The trade-offs at the heart of the case

Years at the end cannot fix every problem at the start

A longer agreement adds potential receipts late in the project’s life. It may do little to fund a payment to an equipment supplier due this month. A lender also cares about production degradation, remaining land rights and the cost of replacing equipment during the extension. A tariff that yields a positive lifetime return can still fail a debt payment in the first operating year. Show both tests before describing a project as financeable.

Bring a replacement bid to the renegotiation

The buyer should know what comparable, delivered power would cost if the project were retendered. Estimate the delay, interim electricity purchases and the risk that another bidder faces the same equipment prices. The original low tariff is no longer a realistic alternative if no financeable project will deliver it. A concession nevertheless needs a defensible limit. Comparing relief with an executable replacement gives the procurer a limit that both investors and other bidders can evaluate.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    How much does a four-year extension add to value today?

  2. Q2

    Which lender covenant might still fail after extension?

  3. Q3

    What evidence would distinguish cost shock from a strategically low bid?

  4. Q4

    Which costs would be incurred if the project were retendered?

  5. Q5

    Why might a longer agreement fail to unlock construction finance?

Frameworks worth applying
  • Reverse auctions and the winner’s curse
  • Contract renegotiation
  • Project finance
  • Commodity price risk
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

LSS4 shows the winner’s curse in reverse auctions: aggressive bids that assumed ever-cheaper equipment became uneconomic when costs rose. Extending contract length, rather than raising tariffs, kept projects alive while leaving the low headline price intact.

  1. Test bids for realism

    Screen out bids that rely on optimistic cost assumptions.

  2. Use indexation where justified

    Allow limited adjustment for verified cost shocks.

  3. Set clear renegotiation rules

    Publish criteria for any contract changes.

What this plan gives up

Rescuing distressed projects secures supply but weakens the discipline of competitive bidding.

The strongest counter-argument

Extending PPAs rewards bidders who underpriced their risk and may encourage aggressive bids in later rounds. Equipment also degrades, so the extra years may yield less than expected.

Metrics to watch

  • Commissioning of LSS4 plants
  • Bid levels in later LSS rounds
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 25 November 2026. Check the source before quoting. Corrections: let us know through the solution form.