Case study · PeruWind generation2018 commissioningLast reviewed 22 November 2026

Peru case studiesAmericas case studies

Enel Green Power Perú

What could Wayra I promise a power buyer about an uncertain wind resource?

A power buyer can purchase electricity whenever the wind blows or demand a fixed quantity at a fixed hour. Those promises have different values, even when their expected annual energy is identical. Wayra I offers a concrete way to price the difference.

Suggested for: MBA strategy · Corporate finance · Facts as of 22 November 2026

Installed capacity132 MW
Turbines42
Expected annual output at launchAbout 600 GWh
01 · The situation

What happened

Enel announced the commissioning of Wayra I in June 2018. The ministry’s project summary describes 42 turbines, 132 megawatts of capacity and estimated annual production of around 600 gigawatt-hours. At continuous full capacity the plant would produce roughly 1,156 gigawatt-hours per ordinary year. Dividing the estimate by that ceiling implies a capacity factor of about 52%. The estimate at commissioning is a benchmark for evaluating a forecast. It does not establish the plant’s subsequent measured performance.

For a buyer, the same capacity factor can describe two very different resources. Output spread over hours of expensive demand is worth more than identical output clustered when neighbouring plants are also generating heavily. A fixed delivery contract can require the seller to replace missing energy at spot prices. When a regional lull coincides with expensive replacement power, the money needed to honour the contract rises precisely when generation revenue falls.

Draw a small table with contracted output, actual metered output, spot price and the contractual settlement for the same hour. A shortfall in a cheap hour can have less financial impact than a much smaller shortfall in an expensive one. If the contracts cover annual rather than hourly delivery, the settlement rule could allow some excess output to offset a previous deficit. The relevant economic exposure changes accordingly. A percentage of expected annual energy is therefore an incomplete description of hedging. What matters is the amount deliverable during the specific period that generates a liability. Look for consecutive weak periods and restrictions on carrying energy credits forward. This is where the wind resource, sales contract and project cash account meet.

Wayra I is a wind farm in Marcona, in the Ica region of southern Peru, built by Enel Green Power Peru. When it began operating in June 2018, it was Peru’s largest wind farm.

It has 42 turbines and a capacity of 132 megawatts. Enel invested more than US$165 million in its construction.

The project won a contract in Peru’s fourth public renewable energy tender and is supported by a 20-year energy supply contract with the Ministry of Energy and Mines. With Wayra I and the Rubí solar plant, Enel became the country’s leading renewable energy generator.

At launch, Enel expected the wind farm to generate about 600 gigawatt-hours a year. If it ran at full capacity every hour, it would produce about 1,156 gigawatt-hours, so the expected output implies a capacity factor of roughly 52 percent, high by international standards and a reflection of strong, steady winds in Marcona.

The capacity factor is central to the economics of wind power. Two wind farms with the same capacity can earn very different revenues if one is in a windier location.

Electricity from Wayra I flows into Peru’s national grid through the Poroma substation. Grid constraints can limit how much energy a plant can deliver, even when the wind is blowing.

Enel later planned a 165 megawatt extension of Wayra, supported by European Investment Bank financing, showing how a successful first phase can lead to further investment.

Wind power has grown rapidly worldwide as costs have fallen, and Latin American countries including Chile, Brazil and Peru have used auctions to attract investment.

Wind output varies by season and time of day. In Marcona, coastal winds are strong for much of the year, but generation still fluctuates, which is why grid operators must balance wind power with other sources.

For investors, the 20-year contract reduces price risk, but output risk remains: if the wind is weaker than expected, revenue falls. Long-term wind measurement before construction is therefore essential.

The capacity factor estimate at commissioning is a benchmark, not a guarantee, and actual output over many years is the true test of the investment.

Wayra I’s success helped establish Marcona as a hub for wind energy in Peru, attracting further investment in the area.

Its performance data also help lenders and investors price future wind projects in Peru, because actual generation records reduce uncertainty about how much energy similar sites can produce. In this way, the first large projects in a new market create valuable information for the projects that follow, lowering financing costs over time.

Data, in this sense, is itself an asset.

02 · Timeline

Key moments

  1. Wayra I entered service in Ica.

  2. Expected annual output was approximately 600 GWh.

03 · Exhibit
Exhibit 1 · Wayra I: expected output versus theoretical maximum
GWh per year600Expected annual output1,156Output at continuous full capacity

Sources: Enel; the maximum is 132 MW × 8,760 hours.

04 · Core tensions

The trade-offs at the heart of the case

Price the shortage that occurs across several assets at once

A regional lull can make wind replacement power expensive and a widespread drought can do the same for hydropower. Reading the two cases together helps distinguish independent plant failures from shared weather risks that diversification within one region may not remove.

Our assessment

I would evaluate a firm delivery offer against hourly wind, prices and projected maintenance windows. Keep a separate estimate for transmission constraints, because the turbine meter and the customer delivery point measure different things. For a lender, inspect the weakest cash month in a sequence of poor months. A reasonable annual expectation does little for an instalment due before the wind returns.

05 · Discussion questions

For your seminar, paper or interview

  1. Q1

    How would two wind sites with the same annual output earn different revenues?

  2. Q2

    Who finances replacement power under a firm contract?

  3. Q3

    What does the implied capacity factor actually measure?

  4. Q4

    How would the decision change if the two adverse events were correlated or could occur together?

  5. Q5

    What additional value should the decision maker assign to avoiding a cash shortage during the severe event?

Frameworks worth applying
  • Renewable auctions
  • Capacity factor
  • Power purchase agreements
  • Wind economics
06 · Our view

How we would approach it

Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.

We think Wayra I shows why wind farms are valued on energy delivered, not installed capacity. Its strong expected capacity factor reflects Marcona’s excellent winds, but actual output and grid availability determine whether revenues match expectations.

  1. Monitor output

    Compare actual generation with forecasts.

  2. Secure grid access

    Avoid curtailment at the substation.

  3. Use long contracts

    Lock in prices through auctions.

What this plan gives up

Wind power is cheap to run but output varies with the weather.

The strongest counter-argument

Some argue gas-fired plants offer more reliable supply in Peru.

Metrics to watch

  • Annual generation
  • Capacity factor
07 · Your turn

Propose your solution

Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.

Submissions are moderated and must relate to this case. Your name, programme and text are stored on our hosting provider and may be published; no email address is collected. Please don’t include personal contact details or confidential information.

Published solutions

Loading published solutions…

Sources

Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.