What happened
Later that year the government requested cancellation of unused financing. The restructuring paper put the amount in the relevant disbursement category at US$6.14 million equivalent. This was not the plant’s construction cost or a calculation of profit. The overall renewable energy project also included activities beyond the Feni plant. Dividing the entire national financing package by the plant’s megawatts would therefore produce a misleading unit cost.
The 25 MW expansion raised installed capacity by half relative to the original design. How much additional revenue it could earn depends on the hours when those panels generate, the capacity of the grid connection and the price or value of electricity at those times. Added solar capacity tends to produce at the same hours as the existing panels. A grid already constrained at midday may receive materially less than the increase in nameplate capacity suggests.
An owner should compare the cost of extra panels with alternatives such as improved evacuation capacity, better maintenance or returning more unused financing. A commissioning date makes it possible to replace forecasts with observed generation, but only after accounting for weather, downtime and system curtailment. Record potential and delivered output separately. That distinction allows the lender to judge whether future shortfalls belong with plant operations or with the network that receives the electricity.
The Sonagazi plant in Feni district was built by the state-owned Electricity Generation Company of Bangladesh under the World Bank’s Scaling Up Renewable Energy Project. Originally planned at 50 MW, it was revised to 75 MW (AC), with 96.34 MW (DC) of panels installed on about 285 acres.
EGCB lists the EPC contract price at US$70 million, awarded to a joint venture of Trina Solar and HYDC of China, with financing from IDA and the government. The plant first delivered power to the grid on 24 February 2024 and its commercial operation date was declared as 1 April 2024.
The World Bank describes Sonagazi as Bangladesh’s first 75 MW grid-tied solar plant and says the overall project added 338 MW of renewable capacity to the national grid. EGCB has since planned further solar plants at the same site.
The difference between AC and DC capacity is a useful lesson for investors. Developers often install more panel capacity than the inverters can export, because panels rarely produce their full rating. This raises output in the mornings, evenings and cloudy periods. When comparing solar projects anywhere in the world, it helps to check which capacity figure is quoted and to look at expected annual energy, which is what generates revenue. Those annual numbers, published openly, also help future projects borrow more cheaply.
Key moments
Renewable energy financing project approved.
Commercial operation began at Sonagazi.
Government requested cancellation of unused financing in the relevant category.
Source: World Bank, World Development Indicators (EG.ELC.RNEW.ZS).
The trade-offs at the heart of the case
Value the extra twenty-five megawatts separately
Reconstruct the last design before the cost decline and compare it with the revised plant. Allocate common civil and grid costs only where they actually increased. The additional capacity might deliver energy cheaply because the site and connection were already funded. It might also face a sharply lower marginal value during midday peaks. I would compare observed curtailment, meter readings and maintenance expense against a weather-adjusted output estimate. If the connection becomes the effective limit, the next investment should be evaluated on released delivery during constrained hours. A headline reduction in panel prices gives no automatic answer about the value of that next taka. An especially useful comparison is the plant’s output during the hours when the original design would already have filled the available connection. Additional panels producing in those hours may bring little extra delivery. The same equipment may still generate additional saleable power earlier in the morning or later in the afternoon.
A capacity increase can carry two different risks
At Sonagazi the physical design expanded as panel costs fell. At Ghorashal a trial approached the planned capacity but a mechanical problem limited sustained operation. The two projects highlight different reasons a megawatt rating may fail to become electricity sold. For solar, weather and the receiving network determine how frequently the rating can be used. For the repowered thermal station, fuel and the condition of both turbines matter. A lender comparing technologies should value the timing of dependable output and include maintenance and constraints on delivery. Merely dividing historical financing by the largest stated megawatt figure would give the appearance of comparability while ignoring the very differences that determine the value of each investment to the grid.
For your seminar, paper or interview
- Q1
How much additional installed capacity did the revision buy?
- Q2
When would another solar panel have little marginal value?
- Q3
Why is cancelling undrawn credit different from reporting a cash profit?
- Capacity factor
- AC and DC capacity
- Land use
- Public utility investment
How we would approach it
Simplifying Finance’s opinion, offered as a starting point for debate, not as fact or investment advice.
We would judge Sonagazi on the energy it delivers each year, not on its headline megawatts. Solar output depends on sunlight, panels and grid availability, so the useful number for a buyer or lender is megawatt-hours sold per taka invested.
Publish annual output
Report megawatt-hours delivered and compare them with the design estimate.
Sign a clear power contract
Agree a tariff and dispatch rules so the plant is paid for all the energy it can produce.
Use the site again
Plan further phases on nearby land to share grid connection and operations costs.
What this plan gives up
Building more on the same site saves on connection costs but concentrates risk from storms, flooding and grid outages in one location.
The strongest counter-argument
Some argue that state utilities should leave solar generation to private developers and focus on transmission, because competitive tenders can deliver cheaper power.
Metrics to watch
- Annual energy delivered
- Grid curtailment hours
Propose your solution
Pick a discussion question and set out what you would do, why, and what it would cost. Strong, well-argued answers are reviewed and published below with your first name and programme.
Published solutions
Loading published solutions…
- World Bank: Feni capacity revision and commercial operation, November 2024 ↗
- World Bank: Original SREP financing and Feni component design ↗
- World Bank: World Development Indicators, Renewable electricity output ↗
- EGCB: Sonagazi 75 MW Solar Power Plant ↗
- World Bank: Powering Bangladesh’s future with renewable energy ↗
- pv magazine: Bangladeshi utility completes 75 MW solar project ↗
- World Bank: Scaling-up Renewable Energy Project (P161869) ↗
- Photo: Country’s largest solar power plant inaugurated.png by Ronitsunny, CC BY-SA 4.0 (cropped and resized) ↗
Figures are as reported by the companies or cited outlets as of 22 November 2026. Check the source before quoting. Corrections: let us know through the solution form.